3. Labour:
| bag @ Tk. 395.00 per bag = Tk. cft @ Tk. 1,400.00 per % cft = Tk. no @ Tk. 600.00 each = Tk. no @ Tk. 390.00 each = Tk. no @ Tk. 320.00 each = Tk. | 39.50 7.00 150.00 195.00 160.00 |
Sub - Total = Tk. Profit 10.00% = Tk. Overhead 3.50% = Tk. | 2,194.50 219.45 76.81 | |
Total = Tk. | 2,490.76 | |
Add VAT with | adjustment factor 1.06383 6.00% = Tk. | 158.98 |
| Grand Total = Tk. | 2,649.74 |
| Rate per No. = Tk. | 2,649.74 |
| Say, Tk. 2,650 .00 each |
|
26.5.2.3 Special coloured 530x450x290 mm 14.5 kg |
|
|
Considering 1 No. of fixture 1. Special coloured long pan: 1 | no @ Tk. 1,972.00 each = Tk. | 1,972.00 |
2. Fitting fixing materials: |
|
|
(a) Cement mortar (1:4)
| bag @ Tk. 395.00 per bag = Tk. | 39.50 |
| cft @ Tk. 1,400.00 per % cft = Tk. | 7.00 |
3. Labour: |
|
|
| no @ Tk. 600.00 each = Tk. | 150.00 |
| no @ Tk. 390.00 each = Tk. | 195.00 |
| no @ Tk. 320.00 each = Tk. | 160.00 |
| Sub - Total = Tk. | 2,523.50 |
| Profit 10.00% = Tk. | 252.35 |
| Overhead 3.50% = Tk. | 88.32 |
| Total = Tk. | 2,864.17 |
Add VAT with | adjustment factor 1.06383 6.00% = Tk. | 182.82 |
| Grand Total = Tk. | 3,046.99 |
| Rate per No. = Tk. | 3,046.99 |
| Say, Tk. 3,047 .00 each |
|
|
|
|
Item No.- 26.6 |
| |
Supplying, fitting and fixing Bangladesh pattern long pan, made of Vitreous China White colour 525x295x285, 5.7kg |
| |
Considering 1 No. of fixture |
|
|
1. White long pan: 1 | no @ Tk. 550.00 each = Tk. | 550.00 |
2. Fitting fixing materials: |
|
|
(a) Cement mortar (1:4)
| bag @ Tk. 395.00 per bag = Tk. | 39.50 |
| cft @ Tk. 1,400.00 per % cft = Tk. | 7.00 |
3. Labour: |
|
|
| no @ Tk. 600.00 each = Tk. | 150.00 |
| no @ Tk. 390.00 each = Tk. | 195.00 |
| no @ Tk. 320.00 each = Tk. | 160.00 |
| Sub - Total = Tk. | 1,101.50 |
| Profit 10.00% = Tk. | 110.15 |
| Overhead 3.50% = Tk. | 38.55 |
| Total = Tk. | 1,250.20 |
Add VAT with | adjustment factor 1.06383 6.00% = Tk. | 79.80 |
| Grand Total = Tk. | 1,330.00 |
| Rate per No. = Tk. | 1,330.00 |
| Say, Tk. 1,330 .00 each |
|