Labour: Plumber 0.15 no @ Tk. 600.00 Skilled labour 0.2 no @ Tk. 390.00 Ordinary labour 0.4 no @ Tk. 320.00 Profit Overhead | each | = = = | Tk. | 90.00 78.00 128.00 | |
Sub - Total 10.00% 3.50% | = = = | Tk. | 3,277.00 327.70 114.70 | ||
Total | = | Tk. | 3,719.40 | ||
| Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 237.41 |
|
| Grand Total | = | Tk. | 3,956.81 |
|
| Rate per No. | = | Tk. | 3,956.81 |
| Say, Tk. 3,957 .00 each |
|
|
| |
|
|
|
|
|
|
Item No.- 26.14 |
|
|
|
| |
Supplying, fitting and fixing glazed vitreous china flat or squatting urinal 510x380x85 mm in size, 9.5 kg |
|
|
|
| |
26.14.1 | White flat/squatting urinal (Bangladeshi), size 510 x 380 x 85 mm, wt. 9.5 kgor equivalent |
|
|
|
|
| Considering 1 No. of fixture |
|
|
|
|
1. | White flat/squatting urinal 1 no @ Tk. 950.00 | each | = | Tk. | 950.00 |
2. | Fitting fixing materials: |
|
|
|
|
(a) | Cement mortar (1:4) |
|
|
|
|
Cement 0.2 bag @ Tk. 395.00 | per bag | = | Tk. | 79.00 | |
Sand (F.M. 1.2) 0.1 cft @ Tk. 1,400.00 | per % cft | = | Tk. | 1.40 | |
3. | Labour: |
|
|
|
|
Plumber 0.2 no @ Tk. 600.00 | each | = | Tk. | 120.00 | |
Skilled labour 0.25 no @ Tk. 390.00 | each | = | Tk. | 97.50 | |
Ordinary labour 0.5 no @ Tk. 320.00 | each | = | Tk. | 160.00 | |
|
| Sub - Total | = | Tk. | 1,407.90 |
| Profit | 10.00% | = | Tk. | 140.79 |
| Overhead | 3.50% | = | Tk. | 49.28 |
|
| Total | = | Tk. | 1,597.97 |
| Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 102.00 |
|
| Grand Total | = | Tk. | 1,699.97 |
|
| Rate per No. | = | Tk. | 1,699.97 |
| Say, Tk. 1,700 .00 each |
|
|
| |
26.14.2 | Coloured flat/squatting urinal (Bangladeshi), size 510 x 380 x 85 mm, wt. 9.5 kg or equivalent |
|
|
|
|
| Considering 1 No. of fixture |
|
|
|
|
1. | Coloured flat/squatting urinal 1 no @ Tk. 1,000.00 | each | = | Tk. | 1,000.00 |
2. | Fitting fixing materials: |
|
|
|
|
(a) | Cement mortar (1:4) |
|
|
|
|
Cement 0.2 bag @ Tk. 395.00 | per bag | = | Tk. | 79.00 | |
Sand (F.M. 1.2) 0.1 cft @ Tk. 1,400.00 | per % cft | = | Tk. | 1.40 | |
3. | Labour: |
|
|
|
|
Plumber 0.2 no @ Tk. 600.00 | each | = | Tk. | 120.00 | |
Skilled labour 0.25 no @ Tk. 390.00 | each | = | Tk. | 97.50 | |
Ordinary labour 0.5 no @ Tk. 320.00 | each | = | Tk. | 160.00 | |
|
| Sub - Total | = | Tk. | 1,457.90 |
| Profit | 10.00% | = | Tk. | 145.79 |
| Overhead | 3.50% | = | Tk. | 51.03 |
|
| Total | = | Tk. | 1,654.72 |
| Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 105.62 |
|
| Grand Total | = | Tk. | 1,760.34 |
|
| Rate per No. | = | Tk. | 1,760.34 |
| Say, Tk. 1,760 .00 each |
|
|
| |
26.14.3 | Special coloured flat/squatting urinal (Bangladeshi), size 510 x 380 x 85 mm, wt. 9.5 kg |
|
|
|
|
| Considering 1 No. of fixture |
|
|
|
|
1. | Special Coloured flat/squatting urinal 1 no @ Tk. 1,100.00 | each | = | Tk. | 1,100.00 |