(b) | Fittings fixing materials: |
|
|
|
|
|
|
|
|
|
(i) | Teflon Tape | 2 | pcs | @ | Tk. | 16.00 | per pcs | = | Tk. | 32.00 |
(d) | Labour: |
|
|
|
|
|
|
|
|
|
Plumber | 0.03 | nos | @ | Tk. | 600.00 | each | = | Tk. | 18.00 | |
Skilled labour | 0.08 | nos | @ | Tk. | 390.00 | each | = | Tk. | 31.20 | |
Ordinary labour | 0.06 | nos | @ | Tk. | 320.00 | each | = | Tk. | 19.20 | |
|
|
|
|
|
|
| Sub - Total | = | Tk. | 918.40 |
|
|
|
|
|
| Profit | 10.00% | = | Tk. | 91.84 |
|
|
|
|
|
| Overhead | 3.50% | = | Tk. | 32.14 |
|
|
|
|
|
|
| Total | = | Tk. | 1,042.38 |
| Add VAT with adjustment factor |
|
|
| 1.06383 | 6.00% | = | Tk. | 66.53 | |
|
|
|
|
|
|
| Grand Total | = | Tk. | 1,108.91 |
|
|
|
| Say, | Tk. | 1,109 .00 each |
|
|
| |
|
|
|
|
| ||||||
Item No.- 26.42 |
|
|
|
|
|
|
|
|
| |
26.42.1 | 100 mm dia uPVC |
|
|
|
|
|
|
|
|
|
| Considering 20 ft. long 1 No. pipe |
|
|
|
|
|
|
|
|
|
100 mm dia 20'-0" long uPVC pipe: | 20 | ft. | @ | Tk. | 79.00 | per ft | = | Tk. | 1,580.00 | |
Fittings |
|
|
|
|
|
|
|
|
| |
(i) | Bend | 1 | nos | @ | Tk. | 146.00 | each | = | Tk. | 146.00 |
Jointing materials |
|
|
|
|
|
|
|
|
| |
(i) | Solvent cement | 54 | ml | @ | Tk. | 0.70 | per ml | = | Tk. | 37.80 |
Excavation | 26.13 | cft | @ | Tk. | 2,958.33 | per % 0 cft | = | Tk. | 77.30 | |
Bedding by sand (F.M. 1.2) | 9.88 | cft | @ | Tk. | 1,400.00 | per cft | = | Tk. | 138.32 | |
Labour: |
|
|
|
|
|
|
|
|
| |
Plumber | 0.2 | nos | @ | Tk. | 600.00 | each | = | Tk. | 120.00 | |
Skilled labour | 0.4 | nos | @ | Tk. | 390.00 | each | = | Tk. | 156.00 | |
Ordinary labour | 0.8 | nos | @ | Tk. | 320.00 | each | = | Tk. | 256.00 | |
|
|
|
|
|
|
| Sub - Total | = | Tk. | 2,511.42 |
|
|
|
|
|
| Profit | 10.00% | = | Tk. | 251.14 |
|
|
|
|
|
| Overhead | 3.50% | = | Tk. | 87.90 |
|
|
|
|
|
|
| Total | = | Tk. | 2,850.46 |
|
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 181.94 | ||
|
|
|
|
|
|
| Grand Total | = | Tk. | 3,032.40 |
|
|
|
|
|
|
| Rate per ft | = | Tk. | 151.62 |
|
|
|
|
|
|
| Rate Per m | = | Tk. | 497.47 |
26.42.2 | 150 mm dia uPVC |
|
| Say, | Tk. | 497 .00 per meter |
|
|
| |
|
|
|
|
| ||||||
| Considering 20 ft. long 1 No. pipe |
|
|
|
|
|
|
|
|
|
150 mm dia 20'-0" long uPVC pipe: | 20 | ft. | @ | Tk. | 167.00 | per ft | = | Tk. | 3,340.00 | |
Jointing materials |
|
|
|
|
|
|
|
|
| |
(i) | Solvent cement | 120 | ml | @ | Tk. | 0.70 | per ml | = | Tk. | 84.00 |
Excavation | 72.04 | cft | @ | Tk. | 2,958.33 | per % 0 cft | = | Tk. | 213.12 | |
Bedding by sand (F.M. 1.2) | 12.36 | cft | @ | Tk. | 1,400.00 | per cft | = | Tk. | 173.04 | |
Labour: |
|
|
|
|
|
|
|
|
| |
Plumber | 0.25 | no | @ | Tk. | 600.00 | each | = | Tk. | 150.00 | |
Skilled labour | 0.5 | no | @ | Tk. | 390.00 | each | = | Tk. | 195.00 | |
Ordinary labour | 0.5 | no | @ | Tk. | 320.00 | each | = | Tk. | 160.00 | |
|
|
|
|
|
|
| Sub - Total | = | Tk. | 4,315.16 |
|
|
|
|
|
| Profit | 10.00% | = | Tk. | 431.52 |
|
|
|
|
|
| Overhead | 3.50% | = | Tk. | 151.03 |
|
|
|
|
|
|
| Total | = | Tk. | 4,897.71 |
|
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 312.62 | ||
|
|
|
|
|
|
| Grand Total | = | Tk. | 5,210.33 |
|
|
|
|
|
|
| Rate per ft | = | Tk. | 260.52 |
|
|
|
|
|
|
| Rate Per m | = | Tk. | 854.77 |
|
|
|
| Say, | Tk. | 855 .00 per meter |
|
|
| |