Item No.- 26.43 |
|
|
|
|
|
|
|
| |
26.43.1 | 150 mm dia RCC pipe made of stone chips, thickness 40 mm |
|
|
|
|
|
|
|
|
| Considering 1.83 m long 3 nos pipe = 5.49 m work |
|
|
|
|
|
|
|
|
1. | 150 mm dia 1.83 m long RCC pipe: 3 nos | @ | Tk. |
| 1,017.00 | each | = | Tk. | 3,051.00 |
2. | Jointing materials |
|
|
|
|
|
|
|
|
Hem 1.35 sqm | @ | Tk. |
| 30.00 | per sqm. | = | Tk. | 40.50 | |
Cement mortar (1:4) |
|
|
|
|
|
|
|
| |
Cement 0.2 bag | @ | Tk. |
| 395.00 | per bag | = | Tk. | 79.00 | |
Sand (F.M. 1.2) 0.52 cft | @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 7.28 | |
3. | excavation 72.75 cft | @ | Tk. |
| 2,958.33 | per % 0 cft | = | Tk. | 215.22 |
4. | Bedding by sand (F.M. 1.2) 12.78 cft | @ | Tk. |
| 1,400.00 | per cft | = | Tk. | 178.92 |
5. | Labour: |
|
|
|
|
|
|
|
|
Plumber 0.25 no | @ | Tk. |
| 600.00 | each | = | Tk. | 150.00 | |
Skilled labour 0.5 no | @ | Tk. |
| 390.00 | each | = | Tk. | 195.00 | |
Ordinary labour 0.5 no | @ | Tk. |
| 320.00 | each | = | Tk. | 160.00 | |
|
|
|
|
|
| Sub - Total | = | Tk. | 4,076.92 |
|
|
|
| Profit | 10.00% | = | Tk. | 407.69 | |
|
|
|
| Overhead | 3.50% | = | Tk. | 142.69 | |
|
|
|
|
|
| Total | = | Tk. | 4,627.30 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 295.36 | ||
|
|
|
|
|
| Grand Total | = | Tk. | 4,922.66 |
|
|
|
|
|
| Rate per m | = | Tk. | 896.66 |
|
| Say, | Tk. |
| 897 | .00 per meter |
|
|
|
26.43.2 | 225 mm dia RCC pipe made of stone chips, thickness 40 mm |
|
|
|
|
|
|
|
|
| Considering 1.83 m long 3 nos pipe = 5.49 m work |
|
|
|
|
|
|
|
|
1. | 225 mm dia 1.83 m long RCC pipe: 3 nos | @ | Tk. |
| 1,575.00 | each | = | Tk. | 4,725.00 |
2. | Jointing materials |
|
|
|
|
|
|
|
|
Hem 1.75 sqm | @ | Tk. |
| 30.00 | per sqm. | = | Tk. | 52.50 | |
Cement mortar (1:4) |
|
|
|
|
|
|
|
| |
Cement 0.31 bag | @ | Tk. |
| 395.00 | per bag | = | Tk. | 122.45 | |
Sand (F.M. 1.2) 0.8 cft | @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 11.20 | |
3. | Excavation 137.73 cft | @ | Tk. |
| 2,958.33 | per % 0 cft | = | Tk. | 407.45 |
4. | Bedding by sand (F.M. 1.2) 18.0 cft | @ | Tk. |
| 1,400.00 | per cft | = | Tk. | 252.00 |
5. | Babour: |
|
|
|
|
|
|
|
|
Plumber 0.5 no | @ | Tk. |
| 600.00 | each | = | Tk. | 300.00 | |
Skilled labour 0.5 no | @ | Tk. |
| 390.00 | each | = | Tk. | 195.00 | |
Ordinary labour 1 no | @ | Tk. |
| 320.00 | each | = | Tk. | 320.00 | |
|
|
|
|
|
| Sub - Total | = | Tk. | 6,385.60 |
|
|
|
| Profit | 10.00% | = | Tk. | 638.56 | |
|
|
|
| Overhead | 3.50% | = | Tk. | 223.50 | |
|
|
|
|
|
| Total | = | Tk. | 7,247.66 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 462.62 | ||
|
|
|
|
|
| Grand Total | = | Tk. | 7,710.28 |
|
|
|
|
|
| Rate per m | = | Tk. | 1,404.42 |
|
| Say, | Tk. |
| 1,404 | .00 per meter |
|
|
|
26.43.3 | 300 mm dia RCC pipe made of stone chips, thickness 50 mm |
|
|
|
|
|
|
|
|
| Considering 1.83 m long 3 nos pipe = 5.49 m work |
|
|
|
|
|
|
|
|
1. | 300 mm dia 1.83 m long RCC pipe: 3 nos | @ | Tk. |
| 2,743.00 | each | = | Tk. | 8,229.00 |
2. | Jointing materials |
|
|
|
|
|
|
|
|
Hem 2.19 sqm | @ | Tk. |
| 30.00 | per sqm. | = | Tk. | 65.70 | |
Cement mortar (1:4) |
|
|
|
|
|
|
|
| |
Cement 0.4 bag | @ | Tk. |
| 395.00 | per bag | = | Tk. | 158.00 | |
Sand (F.M. 1.2) 1 cft | @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 14.00 | |
3. | Excavation 175.16 cft | @ | Tk. |
| 2,958.33 | per % 0 cft | = | Tk. | 518.18 |
4. | Bedding by sand (F.M. 1.2) 21.96 cft | @ | Tk. |
| 1,400.00 | per cft | = | Tk. | 307.44 |
5. | Labour: |
|
|
|
|
|
|
|
|
Plumber 0.5 no | @ | Tk. |
| 600.00 | each | = | Tk. | 300.00 | |
Skilled labour 0.5 no | @ | Tk. |
| 390.00 | each | = | Tk. | 195.00 | |
Ordinary labour 2 nos | @ | Tk. |
| 320.00 | each | = | Tk. | 640.00 | |