Item No.- 26.43

 

 

 

 

 

 

 

 

26.43.1

150 mm dia RCC pipe made of stone chips, thickness 40 mm

 

 

 

 

 

 

 

 

 

Considering 1.83 m long 3 nos pipe = 5.49 m work

 

 

 

 

 

 

 

 

1.

150 mm dia 1.83 m long RCC pipe: 3 nos

@

Tk.

 

1,017.00

each

=

Tk.

3,051.00

2.

Jointing materials

 

 

 

 

 

 

 

 

  1.  

Hem 1.35 sqm

@

Tk.

 

30.00

per sqm.

=

Tk.

40.50

  1.  

Cement mortar (1:4)

 

 

 

 

 

 

 

 

  1.  

Cement 0.2 bag

@

Tk.

 

395.00

per bag

=

Tk.

79.00

  1.  

Sand (F.M. 1.2) 0.52 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

7.28

3.

excavation 72.75 cft

@

Tk.

 

2,958.33

per % 0 cft

=

Tk.

215.22

4.

Bedding by sand (F.M. 1.2) 12.78 cft

@

Tk.

 

1,400.00

per cft

=

Tk.

178.92

5.

Labour:

 

 

 

 

 

 

 

 

  1.  

Plumber 0.25 no

@

Tk.

 

600.00

each

=

Tk.

150.00

  1.  

Skilled labour 0.5 no

@

Tk.

 

390.00

each

=

Tk.

195.00

  1.  

Ordinary labour 0.5 no

@

Tk.

 

320.00

each

=

Tk.

160.00

 

 

 

 

 

 

Sub - Total

=

Tk.

4,076.92

 

 

 

 

Profit

10.00%

=

Tk.

407.69

 

 

 

 

Overhead

3.50%

=

Tk.

142.69

 

 

 

 

 

 

Total

=

Tk.

4,627.30

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

295.36

 

 

 

 

 

 

Grand Total

=

Tk.

4,922.66

 

 

 

 

 

 

Rate per m

=

Tk.

896.66

 

 

Say,

Tk.

 

897

.00 per meter

 

 

 

26.43.2

225 mm dia RCC pipe made of stone chips, thickness 40 mm

 

 

 

 

 

 

 

 

 

Considering 1.83 m long 3 nos pipe = 5.49 m work

 

 

 

 

 

 

 

 

1.

225 mm dia 1.83 m long RCC pipe: 3 nos

@

Tk.

 

1,575.00

each

=

Tk.

4,725.00

2.

Jointing materials

 

 

 

 

 

 

 

 

  1.  

Hem 1.75 sqm

@

Tk.

 

30.00

per sqm.

=

Tk.

52.50

  1.  

Cement mortar (1:4)

 

 

 

 

 

 

 

 

  1.  

Cement 0.31 bag

@

Tk.

 

395.00

per bag

=

Tk.

122.45

  1.  

Sand (F.M. 1.2) 0.8 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

11.20

3.

Excavation 137.73 cft

@

Tk.

 

2,958.33

per % 0 cft

=

Tk.

407.45

4.

Bedding by sand (F.M. 1.2) 18.0 cft

@

Tk.

 

1,400.00

per cft

=

Tk.

252.00

5.

Babour:

 

 

 

 

 

 

 

 

  1.  

Plumber 0.5 no

@

Tk.

 

600.00

each

=

Tk.

300.00

  1.  

Skilled labour 0.5 no

@

Tk.

 

390.00

each

=

Tk.

195.00

  1.  

Ordinary labour 1 no

@

Tk.

 

320.00

each

=

Tk.

320.00

 

 

 

 

 

 

Sub - Total

=

Tk.

6,385.60

 

 

 

 

Profit

10.00%

=

Tk.

638.56

 

 

 

 

Overhead

3.50%

=

Tk.

223.50

 

 

 

 

 

 

Total

=

Tk.

7,247.66

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

462.62

 

 

 

 

 

 

Grand Total

=

Tk.

7,710.28

 

 

 

 

 

 

Rate per m

=

Tk.

1,404.42

 

 

Say,

Tk.

 

1,404

.00 per meter

 

 

 

26.43.3

300 mm dia RCC pipe made of stone chips, thickness 50 mm

 

 

 

 

 

 

 

 

 

Considering 1.83 m long 3 nos pipe = 5.49 m work

 

 

 

 

 

 

 

 

1.

300 mm dia 1.83 m long RCC pipe: 3 nos

@

Tk.

 

2,743.00

each

=

Tk.

8,229.00

2.

Jointing materials

 

 

 

 

 

 

 

 

  1.  

Hem 2.19 sqm

@

Tk.

 

30.00

per sqm.

=

Tk.

65.70

  1.  

Cement mortar (1:4)

 

 

 

 

 

 

 

 

  1.  

Cement 0.4 bag

@

Tk.

 

395.00

per bag

=

Tk.

158.00

  1.  

Sand (F.M. 1.2) 1 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

14.00

3.

Excavation 175.16 cft

@

Tk.

 

2,958.33

per % 0 cft

=

Tk.

518.18

4.

Bedding by sand (F.M. 1.2) 21.96 cft

@

Tk.

 

1,400.00

per cft

=

Tk.

307.44

5.

Labour:

 

 

 

 

 

 

 

 

  1.  

Plumber 0.5 no

@

Tk.

 

600.00

each

=

Tk.

300.00

  1.  

Skilled labour 0.5 no

@

Tk.

 

390.00

each

=

Tk.

195.00

  1.  

Ordinary labour 2 nos

@

Tk.

 

320.00

each

=

Tk.

640.00