|
| Profit | Sub - Total 10.00% 3.50% | = = = | Tk. | 10,427.32 1,042.73 364.96 |
Total | = | Tk. | 11,835.01 | |||
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 755.43 |
|
|
| Grand Total | = | Tk. | 12,590.44 |
|
|
| Rate per m | = | Tk. | 2,293.34 |
| Say, Tk. | 2,293 | .00 per meter |
|
|
|
26.43.4 | 375 mm dia RCC pipe made of stone chips, thickness 50 mm |
|
|
|
|
|
| Considering 1.83 m long 3 nos pipe = 5.49 m work |
|
|
|
|
|
1. | 375 mm dia 1.83 m long RCC pipe: 3 nos @ Tk. | 3,580.00 | each | = | Tk. | 10,740.00 |
2. | Jointing materials |
|
|
|
|
|
Hem 2.73 sqm @ Tk. | 30.00 | per sqm. | = | Tk. | 81.90 | |
Cement mortar (1:4) |
|
|
|
|
| |
Cement 0.47 bag @ Tk. | 395.00 | per bag | = | Tk. | 185.65 | |
Sand (F.M. 1.2) 1.18 cft @ Tk. | 1,400.00 | per % cft | = | Tk. | 16.52 | |
3. | Excavation 217.89 cft @ Tk. | 2,958.33 | per % 0 cft | = | Tk. | 644.59 |
4. | Bedding by sand (F.M. 1.2) 26.3 cft @ Tk. | 1,400.00 | per cft | = | Tk. | 368.20 |
5. | Labour: |
|
|
|
|
|
Plumber 0.5 no @ Tk. | 600.00 | each | = | Tk. | 300.00 | |
Skilled labour 1 no @ Tk. | 390.00 | each | = | Tk. | 390.00 | |
Ordinary labour 2 nos @ Tk. | 320.00 | each | = | Tk. | 640.00 | |
|
|
| Sub - Total | = | Tk. | 13,366.86 |
|
| Profit | 10.00% | = | Tk. | 1,336.69 |
|
| Overhead | 3.50% | = | Tk. | 467.84 |
|
|
| Total | = | Tk. | 15,171.39 |
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 968.39 |
|
|
| Grand Total | = | Tk. | 16,139.78 |
|
|
| Rate per m | = | Tk. | 2,939.85 |
| Say, Tk. | 2,940 | .00 per meter |
|
|
|
|
|
|
|
|
|
|
Item No.- 26.44 |
|
|
|
|
| |
| 4" or 100 mm dia uPVC 8 bar waste pipe |
|
|
|
|
|
| Considering 120 ft. work (80' + 40') work |
|
|
|
|
|
| The costing of waste water down pipe - fittings based one one main line connected from 5th floor to ground floor of a 5 storied building |
|
|
|
|
|
(a) | 100 mm dia uPVC pipe 80 ft. @ Tk. | 79.00 | per ft | = | Tk. | 6,320.00 |
(b) | 32 mm dia uPVC pipe 40 ft. @ Tk. | 20.00 | per ft | = | Tk. | 800.00 |
(c) | Fittings: |
|
|
|
|
|
4" dia uPVC door Tee (back) 5 nos @ Tk. | 180.00 | each | = | Tk. | 900.00 | |
4" dia uPVC plain bend 900 1 no @ Tk. | 100.00 | each | = | Tk. | 100.00 | |
4" dia uPVC long trap 5 nos @ Tk. | 212.00 | each | = | Tk. | 1,060.00 | |
4" dia uPVC round grating 5 nos @ Tk. | 295.00 | each | = | Tk. | 1,475.00 | |
4" dia uPVC vent cowl 1 no @ Tk. | 28.00 | each | = | Tk. | 28.00 | |
4" dia uPVC plain bend 900 5 nos @ Tk. | 146.00 | each | = | Tk. | 730.00 | |
(d) | Jointing & fixing materials |
|
|
|
|
|
(i) | Solvent cement for jointing 600 ml @ Tk. | 0.70 | per ml | = | Tk. | 420.00 |
(e) | Labour: |
|
|
|
|
|
Plumber 2 nos @ Tk. | 600.00 | each | = | Tk. | 1,200.00 | |
Skilled labour 2 nos @ Tk. | 390.00 | each | = | Tk. | 780.00 | |
Ordinary labour 2 nos @ Tk. | 320.00 | each | = | Tk. | 640.00 | |
(f) | Scaffolding and sundries |
| LS | = | Tk. | 352.00 |
|
|
| Sub - Total | = | Tk. | 14,805.00 |
|
| Profit | 10.00% | = | Tk. | 1,480.50 |
|
| Overhead | 3.50% | = | Tk. | 518.18 |
|
|
| Total | = | Tk. | 16,803.68 |
| Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 1,072.58 |
|
|
| Grand Total | = | Tk. | 17,876.26 |
|
|
| Rate per ft | = | Tk. | 148.97 |