Prev Next
īģŋ

 

 

Profit
Overhead

Sub - Total

10.00%

3.50%

=

=

=

Tk.
Tk.
Tk.

10,427.32

1,042.73

364.96

Total

=

Tk.

11,835.01

 

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

755.43

 

 

 

Grand Total

=

Tk.

12,590.44

 

 

 

Rate per m

=

Tk.

2,293.34

 

Say, Tk.

2,293

.00 per meter

 

 

 

26.43.4

375 mm dia RCC pipe made of stone chips, thickness 50 mm

 

 

 

 

 

 

Considering 1.83 m long 3 nos pipe = 5.49 m work

 

 

 

 

 

1.

375 mm dia 1.83 m long RCC pipe: 3 nos @ Tk.

3,580.00

each

=

Tk.

10,740.00

2.

Jointing materials

 

 

 

 

 

  1.  

Hem 2.73 sqm @ Tk.

30.00

per sqm.

=

Tk.

81.90

  1.  

Cement mortar (1:4)

 

 

 

 

 

  1.  

Cement 0.47 bag @ Tk.

395.00

per bag

=

Tk.

185.65

  1.  

Sand (F.M. 1.2) 1.18 cft @ Tk.

1,400.00

per % cft

=

Tk.

16.52

3.

Excavation 217.89 cft @ Tk.

2,958.33

per % 0 cft

=

Tk.

644.59

4.

Bedding by sand (F.M. 1.2) 26.3 cft @ Tk.

1,400.00

per cft

=

Tk.

368.20

5.

Labour:

 

 

 

 

 

  1.  

Plumber 0.5 no @ Tk.

600.00

each

=

Tk.

300.00

  1.  

Skilled labour 1 no @ Tk.

390.00

each

=

Tk.

390.00

  1.  

Ordinary labour 2 nos @ Tk.

320.00

each

=

Tk.

640.00

 

 

 

Sub - Total

=

Tk.

13,366.86

 

 

Profit

10.00%

=

Tk.

1,336.69

 

 

Overhead

3.50%

=

Tk.

467.84

 

 

 

Total

=

Tk.

15,171.39

 

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

968.39

 

 

 

Grand Total

=

Tk.

16,139.78

 

 

 

Rate per m

=

Tk.

2,939.85

 

Say, Tk.

2,940

.00 per meter

 

 

 

 

 

 

 

 

 

 

Item No.- 26.44

 

 

 

 

 

 

4" or 100 mm dia uPVC 8 bar waste pipe

 

 

 

 

 

 

Considering 120 ft. work (80' + 40') work

 

 

 

 

 

 

The costing of waste water down pipe - fittings based one one main line connected from 5th floor to ground floor of a 5 storied building

 

 

 

 

 

(a)

100 mm dia uPVC pipe 80 ft. @ Tk.

79.00

per ft

=

Tk.

6,320.00

(b)

32 mm dia uPVC pipe 40 ft. @ Tk.

20.00

per ft

=

Tk.

800.00

(c)

Fittings:

 

 

 

 

 

  1.  

4" dia uPVC door Tee (back) 5 nos @ Tk.

180.00

each

=

Tk.

900.00

  1.  

4" dia uPVC plain bend 900 1 no @ Tk.

100.00

each

=

Tk.

100.00

  1.  

4" dia uPVC long trap 5 nos @ Tk.

212.00

each

=

Tk.

1,060.00

  1.  

4" dia uPVC round grating 5 nos @ Tk.

295.00

each

=

Tk.

1,475.00

  1.  

4" dia uPVC vent cowl 1 no @ Tk.

28.00

each

=

Tk.

28.00

  1.  

4" dia uPVC plain bend 900 5 nos @ Tk.

146.00

each

=

Tk.

730.00

(d)

Jointing & fixing materials

 

 

 

 

 

(i)

Solvent cement for jointing 600 ml @ Tk.

0.70

per ml

=

Tk.

420.00

(e)

Labour:

 

 

 

 

 

  1.  

Plumber 2 nos @ Tk.

600.00

each

=

Tk.

1,200.00

  1.  

Skilled labour 2 nos @ Tk.

390.00

each

=

Tk.

780.00

  1.  

Ordinary labour 2 nos @ Tk.

320.00

each

=

Tk.

640.00

(f)

Scaffolding and sundries

 

LS

=

Tk.

352.00

 

 

 

Sub - Total

=

Tk.

14,805.00

 

 

Profit

10.00%

=

Tk.

1,480.50

 

 

Overhead

3.50%

=

Tk.

518.18

 

 

 

Total

=

Tk.

16,803.68

 

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

1,072.58

 

 

 

Grand Total

=

Tk.

17,876.26

 

 

 

Rate per ft

=

Tk.

148.97