Prev Next
īģŋ

 

 

 

 

 

 

 

Rate per m

=

Tk.

488.77

Say,

Tk.

489

.00 per meter

 

 

 

 

 

 

 

 

 

 

 

 

Item No.- 26.45

 

 

 

 

 

 

 

 

 

26.45.1

150 mm dia uPVC pipe for underground laying

 

 

 

 

 

 

 

 

 

 

Considering 20 ft. long one pipe

 

 

 

 

 

 

 

 

 

  1.  

150 mm uPVC pipe:

20

ft.

@

Tk.

167.00

per ft

=

Tk.

3,340.00

  1.  

Jointing materials

 

 

 

 

 

 

 

 

 

(i)

Solvent cement

50

ml

@

Tk.

0.70

per ml

=

Tk.

35.00

  1.  

Excavation

62.5

cft

@

Tk.

2,958.33

per % 0 cft

=

Tk.

184.90

  1.  

Bedding by sand (F.M. 0.8)

38.8

cft

@

Tk.

1,400.00

per cft

=

Tk.

543.20

  1.  

Labour:

 

 

 

 

 

 

 

 

 

  1.  

Plumber

0.25

no

@

Tk.

600.00

each

=

Tk.

150.00

  1.  

Skilled labour

0.5

no

@

Tk.

390.00

each

=

Tk.

195.00

  1.  

Ordinary labour

0.5

no

@

Tk.

320.00

each

=

Tk.

160.00

 

 

 

 

 

 

 

Sub - Total

=

Tk.

4,608.10

 

 

 

 

 

 

Profit

10.00%

=

Tk.

460.81

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

161.28

 

 

 

 

 

 

 

Total

=

Tk.

5,230.19

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

333.84

 

 

 

 

 

 

 

Grand Total

=

Tk.

5,564.03

 

 

 

 

 

 

 

Rate per ft

=

Tk.

278.20

 

 

 

 

 

 

 

Rate Per m

=

Tk.

912.77

26.45.2

200 mm dia uPVC for underground laying

 

 

Say,

Tk.

913

.00 per meter

 

 

 

 

 

 

 

 

 

Considering 20 ft. long one pipe

 

 

 

 

 

 

 

 

 

  1.  

200 mm uPVC pipe:

20

ft.

@

Tk.

257.00

per ft

=

Tk.

5,140.00

  1.  

Jointing materials

 

 

 

 

 

 

 

 

 

(i)

Solvent cement

50

ml

@

Tk.

0.70

per ml

=

Tk.

35.00

  1.  

Excavation

87.5

cft

@

Tk.

2,958.33

per % 0 cft

=

Tk.

258.85

  1.  

Bedding by sand (F.M. 0.8)

67.5

cft

@

Tk.

1,400.00

per cft

=

Tk.

945.00

  1.  

Labour:

 

 

 

 

 

 

 

 

 

  1.  

Plumber

0.25

no

@

Tk.

600.00

each

=

Tk.

150.00

  1.  

Skilled labour

0.5

no

@

Tk.

390.00

each

=

Tk.

195.00

  1.  

Ordinary labour

0.5

no

@

Tk.

320.00

each

=

Tk.

160.00

 

 

 

 

 

 

 

Sub - Total

=

Tk.

6,883.85

 

 

 

 

 

 

Profit

10.00%

=

Tk.

688.39

 

 

 

 

 

 

Overhead

3.50%

=

Tk.

240.93

 

 

 

 

 

 

 

Total

=

Tk.

7,813.17

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

498.71

 

 

 

 

 

 

 

Grand Total

=

Tk.

8,311.88

 

 

 

 

 

 

 

Rate per ft

=

Tk.

415.59

 

 

 

 

 

 

 

Rate Per m

=

Tk.

1,363.55

26.45.3

250 mm dia uPVC for underground laying

 

 

Say,

Tk.

1,364

.00 per meter

 

 

 

 

 

 

 

 

 

Considering 20 ft. long one pipe

 

 

 

 

 

 

 

 

 

  1.  

250 mm uPVC pipe:

20

ft.

@

Tk.

405.00

per ft

=

Tk.

8,100.00

  1.  

Jointing materials

 

 

 

 

 

 

 

 

 

(i)

Solvent cement

330

ml

@

Tk.

0.70

per ml

=

Tk.

231.00

  1.  

Excavation

87.5

cft

@

Tk.

2,958.33

per % 0 cft

=

Tk.

258.85

  1.  

Bedding by sand (F.M. 0.8)

52.5

cft

@

Tk.

1,400.00

per cft

=

Tk.

735.00

  1.  

Labour:

 

 

 

 

 

 

 

 

 

  1.  

Plumber

0.25

no

@

Tk.

600.00

each

=

Tk.

150.00

  1.  

Skilled labour

0.5

no

@

Tk.

390.00

each

=

Tk.

195.00

  1.  

Ordinary labour

0.5

no

@

Tk.

320.00

each

=

Tk.

160.00

 

 

 

 

 

 

 

Sub - Total

=

Tk.

9,829.85

 

 

 

 

 

 

Profit

10.00%

=

Tk.

982.99