Prev Next
īģŋ

  1. Fuel: @ 4.375 liter per hour 315 liter @ Tk.
  2. Foreman: @ 1 No. per 8 hrs 9 nos @ Tk.
  3. Skilled labour 6 nos @ Tk.
  4. Local carriage, T & P

89.00 per liter

800.00 each

390.00 each

LS

= = = =

Tk. Tk. Tk. Tk.

28,035.00 7,200.00 2,340.00 1,120.00

 

Sub - Total

=

Tk.

66,757.00

 

Profit 10.00%

=

Tk.

6,675.70

 

Overhead 3.50%

=

Tk.

2,336.50

 

Total

=

Tk.

75,769.20

Add VAT with adjustment factor

1.06383 6.00%

=

Tk.

4,836.33

 

Grand Total

=

Tk.

80,605.53

 

Rate per hour

=

Tk.

1,119.52

Say, Tk.

1,120 .00 per hour

 

 

 

 

 

 

 

 

Item No.- 27.39

 

 

 

 

Disinfection of the tube well

 

 

 

 

Cost for disinfection of the tube well including supply of all the materials and other necessary cost as per specification (for 150 x 200 mm tube-well)

LS

=

Tk.

1,766.35

 

Profit 10.00%

=

Tk.

176.64

 

Overhead 3.50%

=

Tk.

61.82

 

Total

=

Tk.

2,004.81

Add VAT with adjustment factor

1.06383 6.00%

=

Tk.

127.97

 

Grand Total

=

Tk.

2,132.78

Say, Tk.

2,133 .00 each

 

 

 

 

 

 

 

 

Item No.- 27.40

 

 

 

 

Filling the bore hole around the well from top to the shrouding to G.L. as per specification

 

 

 

 

Considering 100 meter

  1. Foreman 1 no @ Tk.

800.00 each

=

Tk.

800.00

  1. Skilled labour 9 no @ Tk.

390.00 each

=

Tk.

3,510.00

  1. Local carriage, T & P

LS

=

Tk.

400.00

 

Sub - Total

=

Tk.

4,710.00

 

Profit 10.00%

=

Tk.

471.00

 

Overhead 3.50%

=

Tk.

164.85

 

Total

=

Tk.

5,345.85

Add VAT with adjustment factor

1.06383 6.00%

=

Tk.

341.22

 

Grand Total

=

Tk.

5,687.07

 

Rate per rm

=

Tk.

56.87

Say, Tk.

57 .00 per meter

 

 

 

 

 

 

 

 

Item No.- 27.41

 

 

 

 

Protective top cover

 

 

 

 

Considering for 1 job

  1. 300 mm dia and 6 mm

thick M.S. pipe 1 meter @ Tk.

  1. 6 mm thick 350 mm

dia M.S. plate 1 no @ Tk.

5,448.65 per meter

1,421.27 each

=

=

Tk. Tk.

5,448.65

1,421.27

  1. Welding and other cost as necessary

LS

=

Tk.

800.00

 

Sub - Total

=

Tk.

7,669.92

 

Profit 10.00%

=

Tk.

766.99

 

Overhead 3.50%

=

Tk.

268.45

 

Total

=

Tk.

8,705.36

Add VAT with adjustment factor

1.06383 6.00%

=

Tk.

555.66

 

Grand Total

=

Tk.

9,261.02

Say, Tk.

9,261 .00 each