ANALYSIS FOR INSTALLATION OF 150 mm x 200 mm DIA SHROUDED PRODUCTION WELL WITH G.I. PIPE

 

 

 

 

 

 

 

 

 

Item No.- 27.42.1

 

 

 

 

600 mm dia boring

a) Considering 0 m to 50 meter
Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks

50 meter @

Add VAT with adjustment factor

Tk. 1,059 per meter

Profit 10.00%

Overhead 3.50%

=

=

=

Tk.
Tk.
Tk.

52,950.00

5,295.00

1,853.25

Total

1.06383 6.00%

=

=

Tk. Tk.

60,098.25

3,836.06

Grand Total

Rate per meter (from 0 m to 50 m)

=

=

Tk. Tk.

63,934.31

1,278.69

Say,

Tk. 1,279 .00 per meter

 

Item No.- 27.42.2

 

 

 

 

 

600 mm dia boring

Considering 50 m to 100 m

  1. Rate for 0 m to 50 m
  2. Add for 50 m to 100 m

 

15%

=

=

Tk. Tk.

1,278.69

191.80

Total

Rate per meter (50 m to 100 m)

=

=

Tk. Tk.

1,470.49

1,470.49

Say,

Tk. 1,470 .00 per meter

 

 

 

 

Item No.- 27.42.3

 

 

 

 

 

600 mm dia boring

Considering 100 m to 152 m

  1. Rate for 50 m to 100 m
  2. Add for 100 m to 152 m

 

15%

=

=

Tk. Tk.

1,470.49

220.57

Total

Rate per meter (100 m to 152 m)

=

=

Tk. Tk.

1,691.06

1,691.06

Say, Tk. 1,691 .00 per meter

 

 

 

 

Item No.- 27.42.4

 

 

 

 

 

600 mm dia boring

Considering 152 m to 200 m

  1. Rate for 100 m to 152 m
  2. Add for 152 m to 200 m

 

15%

=

=

Tk. Tk.

1,691.06

253.66

Total

Rate per meter (152 m to 200 m)

=

=

Tk. Tk.

1,944.72

1,944.72

Say, Tk. 1,945 .00 per meter

 

 

 

 

Item No.- 27.42.5

 

 

 

 

 

600 mm dia boring

Considering 200 m to 250 m

  1. Rate for 152 m to 200 m
  2. Add for 200 m to 250 m

 

15%

=

=

Tk. Tk.

1,944.72

291.71

Total

Rate per meter (200 m to 250 m)

=

=

Tk. Tk.

2,236.43

2,236.43

Say, Tk. 2,236 .00 per meter

 

 

 

 

Item No.- 27.42.6

 

 

 

 

 

600 mm dia boring

Beyond 250 m

  1. Rate for 200m to 250 m
  2. Add for beyond 250 m

 

15%

=

=

Tk. Tk.

2,236.43

335.46