ANALYSIS FOR INSTALLATION OF 150 mm x 200 mm DIA SHROUDED PRODUCTION WELL WITH G.I. PIPE |
|
|
|
| |
|
|
|
|
| |
Item No.- 27.42.1 |
|
|
|
| |
600 mm dia boring a) Considering 0 m to 50 meter | 50 meter @ Add VAT with adjustment factor | Tk. 1,059 per meter Profit 10.00% Overhead 3.50% | = = = | Tk. | 52,950.00 5,295.00 1,853.25 |
Total 1.06383 6.00% | = = | Tk. Tk. | 60,098.25 3,836.06 | ||
Grand Total Rate per meter (from 0 m to 50 m) | = = | Tk. Tk. | 63,934.31 1,278.69 | ||
Say, | Tk. 1,279 .00 per meter |
| |||
Item No.- 27.42.2 |
|
|
|
|
|
600 mm dia boring Considering 50 m to 100 m
|
| 15% | = = | Tk. Tk. | 1,278.69 191.80 |
Total Rate per meter (50 m to 100 m) | = = | Tk. Tk. | 1,470.49 1,470.49 | ||
Say, | Tk. 1,470 .00 per meter |
| |||
|
|
| |||
Item No.- 27.42.3 |
|
|
|
|
|
600 mm dia boring Considering 100 m to 152 m
|
| 15% | = = | Tk. Tk. | 1,470.49 220.57 |
Total Rate per meter (100 m to 152 m) | = = | Tk. Tk. | 1,691.06 1,691.06 | ||
Say, Tk. 1,691 .00 per meter |
| ||||
|
|
| |||
Item No.- 27.42.4 |
|
|
|
|
|
600 mm dia boring Considering 152 m to 200 m
|
| 15% | = = | Tk. Tk. | 1,691.06 253.66 |
Total Rate per meter (152 m to 200 m) | = = | Tk. Tk. | 1,944.72 1,944.72 | ||
Say, Tk. 1,945 .00 per meter |
| ||||
|
|
| |||
Item No.- 27.42.5 |
|
|
|
|
|
600 mm dia boring Considering 200 m to 250 m
|
| 15% | = = | Tk. Tk. | 1,944.72 291.71 |
Total Rate per meter (200 m to 250 m) | = = | Tk. Tk. | 2,236.43 2,236.43 | ||
Say, Tk. 2,236 .00 per meter |
| ||||
|
|
| |||
Item No.- 27.42.6 |
|
|
|
|
|
600 mm dia boring Beyond 250 m
|
| 15% | = = | Tk. Tk. | 2,236.43 335.46 |