Prev Next
īģŋ

@ 4.8 liter per hour 345 liter @ Tk.

  1. Foreman: @ 1 No. per 8 hrs 9 nos @ Tk.
  2. Skilled labour 6 nos @ Tk.
  3. Local carriage, T & P

89.00 per liter

800.00 each

390.00 each

LS

= = = =

Tk. Tk. Tk. Tk.

30,705.00 7,200.00 2,340.00 1,120.00

Sub - Total

=

Tk.

71,431.48

 

Profit 10.00%

=

Tk.

7,143.15

 

Overhead 3.50%

=

Tk.

2,500.10

 

Total

=

Tk.

81,074.73

Add VAT with adjustment factor

1.06383 6.00%

=

Tk.

5,174.98

 

Grand Total

=

Tk.

86,249.71

 

Rate per hour

=

Tk.

1,197.91

Say, Tk.

1,198 .00 per hour

 

 

 

 

 

 

 

 

Item No.- 27.54

 

 

 

 

Disinfection of the tube well

 

 

 

 

Cost for disinfection of the tube well including supply of all the materials and other necessary cost as per specification

LS

=

Tk.

2,060.74

 

Profit 10.00%

=

Tk.

206.07

 

Overhead 3.50%

=

Tk.

72.13

 

Total

=

Tk.

2,338.94

Add VAT with adjustment factor

1.06383 6.00%

=

Tk.

149.29

 

Grand Total

=

Tk.

2,488.23

Say, Tk.

2,488 .00 each

 

 

 

 

 

 

 

 

Item No.- 27.55

 

 

 

 

Filling the bore hole around the well from top to the shrouding to G.L. as per specification

 

 

 

 

Considering 100 meter

  1. Foreman 1 no @ Tk.

800.00 each

=

Tk.

800.00

  1. Skilled labour 9 no @ Tk.

390.00 each

=

Tk.

3,510.00

  1. Local carriage, T & P

LS

=

Tk.

400.00

 

Sub - Total

=

Tk.

4,710.00

 

Profit 10.00%

=

Tk.

471.00

 

Overhead 3.50%

=

Tk.

164.85

 

Total

=

Tk.

5,345.85

Add VAT with adjustment factor

1.06383 6.00%

=

Tk.

341.22

 

Grand Total

=

Tk.

5,687.07

 

Rate per rm

=

Tk.

56.87

Say, Tk.

57 .00 per meter

 

 

 

 

 

 

 

 

ANALYSIS FOR INSTALLATION OF 50 mm x 150 mm DIA SHROUDED

 

 

 

 

PRODUCTION WELL WITH G.I. PIPE

 

 

 

 

 

 

 

 

 

Item No.- 27.56.1

 

 

 

 

325 mm dia boring

a) Considering 0 m to 50 m

 

 

 

 

Cost for boring including all equipment, accessories, labours and materials along

with insurance coverage of risks 50 meter @ Tk.

777.65 per meter

=

Tk.

38,882.50

 

Profit 10.00%

=

Tk.

3,888.25

 

Overhead 3.50%

=

Tk.

1,360.89

 

Total

=

Tk.

44,131.64

Add VAT with adjustment factor

1.06383 6.00%

=

Tk.

2,816.91

 

Grand Total

=

Tk.

46,948.55

Rate per meter (from 0 m to 50 m)

=

Tk.

938.97

Say, Tk. 939 .00 per meter