Item No.- 28.1.1 |
|
|
|
|
|
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying Titas Gas. 75 mm ND (88.90 mm O.D) M.S. pipe. Considering 100 rft of pipe line (a) Materials: |
|
|
|
|
|
| Tk. 312.94 | per rft | = | Tk. | 31,294.00 |
| Tk. 6,159.23 | per roll | = | Tk. | 6,159.23 |
(b) Labour: | Tk. 315.00 | per liter | = | Tk. | 357.84 |
100'-0" x 1'-6" x 3'-0"= 450.00 cft @
surface with excavated earth 100 rft @
pipe with tap in/c scrapping 100 rft @ | Tk. 2,958.33 Tk. 14.88 Tk. 9.75 | per % 0 cft | = = = | Tk. | 1,331.25 1,488.00 975.00 |
|
| LS | = | Tk. | 480.00 |
|
| Sub - Total | = | Tk. | 42,085.32 |
| Incidental charges | 10.00% | = | Tk. | 4,208.53 |
| Profit | 10.00% | = | Tk. | 4,208.53 |
| Overhead | 3.50% | = | Tk. | 147.30 |
|
| Total | = | Tk. | 50,649.68 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 3,232.96 |
|
| Grand Total | = | Tk. | 53,882.64 |
|
| Rate per rft | = | Tk. | 538.83 |
|
| Rate per rm | = | Tk. | 1,767.90 |
Say, | Tk. 1,768 | .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 28.1.2 |
|
|
|
|
|
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying |
|
|
|
|
|
Titas Gas. 50 mm ND (60.30 mm O.D) M.S. pipe. |
|
|
|
|
|
Considering 100 rft of pipe line (a) Materials: |
|
|
|
|
|
| Tk. 205.00 | per rft | = | Tk. | 20,500.00 |
| Tk. 1,168.55 | per roll | = | Tk. | 3,505.65 |
(b) Labour: | Tk. 315.00 | per liter | = | Tk. | 238.46 |
(i) Cutting trenches: |
|
|
|
|
|
100'-0" x 1'-6" x 3'-0"= 450.00 cft @
surface with excavated earth 100 rft @
pipe with tap in/c scrapping 100 rft @ | Tk. 2,958.33 Tk. 14.88 Tk. 9.75 | per % 0 cft | = = = | Tk. | 1,331.25 1,488.00 975.00 |
|
| LS | = | Tk. | 480.00 |
|
| Sub - Total | = | Tk. | 28,518.36 |
| Incidental charges | 10.00% | = | Tk. | 2,851.84 |
| Profit | 10.00% | = | Tk. | 2,851.84 |
| Overhead | 3.50% | = | Tk. | 99.81 |
|
| Total | = | Tk. | 34,321.85 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 2,190.76 |
|
| Grand Total | = | Tk. | 36,512.61 |
|
| Rate per rft | = | Tk. | 365.13 |
|
| Rate per rm | = | Tk. | 1,197.99 |
Say, | Tk. 1,198 .00 per meter |
|
|
| |