Item No.- 28.1.3 |
|
|
|
|
|
|
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying Titas Gas 25 mm ND (33.40 mm O.D) M.S. pipe. Considering 100 rft of pipe line (a) Materials: |
|
|
|
|
|
|
| @ | Tk. 100.00 | per rft | = | Tk. | 10,000.00 |
| @ | Tk. 1,168.55 | per roll | = | Tk. | 1,752.83 |
(b) Labour: | @ | Tk. 315.00 | per liter | = | Tk. | 204.75 |
(i) Cutting trenches: |
|
|
|
|
|
|
100'-0" x 1'-6" x 3'-0"= 450.00 cft
surface with excavated earth 100 rft
pipe with tap in/c scrapping 100 rft | @ @ @ | Tk. 2,958.33 Tk. 14.88 Tk. 9.75 | per % 0 cft | = = = | Tk. | 1,331.25 1,488.00 975.00 |
|
|
| LS | = | Tk. | 480.00 |
|
|
| Sub - Total | = | Tk. | 16,231.83 |
|
| Incidental charges | 10.00% | = | Tk. | 1,623.18 |
|
| Profit | 10.00% | = | Tk. | 1,623.18 |
|
| Overhead | 3.50% | = | Tk. | 56.81 |
|
|
| Total | = | Tk. | 19,535.00 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 1,246.92 | |
|
|
| Grand Total | = | Tk. | 20,781.92 |
|
|
| Rate per rft | = | Tk. | 207.82 |
|
|
| Rate per rm | = | Tk. | 681.86 |
| Say, | Tk. 682 | .00 per meter |
|
|
|
|
|
|
|
|
|
|
Item No.- 28.1.4 |
|
|
|
|
|
|
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying |
|
|
|
|
|
|
Titas Gas 20 mm ND (26.7 mm O.D) M.S. pipe. |
|
|
|
|
|
|
Considering 100 rft of pipe line (a) Materials: |
|
|
|
|
|
|
| @ | Tk. 65.00 | per rft | = | Tk. | 6,500.00 |
| @ | Tk. 1,168.55 | per roll | = | Tk. | 1,460.69 |
(b) Labour: | @ | Tk. 315.00 | per liter | = | Tk. | 179.55 |
(i) Cutting trenches: |
|
|
|
|
|
|
100'-0" x 1'-6" x 3'-0"= 450.00 cft
surface with excavated earth 100 rft
with tap in/c scrapping 100 rft | @ @ @ | Tk. 2,958.33 Tk. 14.88 Tk. 9.75 | per % 0 cft | = = = | Tk. | 1,331.25 1,488.00 975.00 |
|
|
| LS | = | Tk. | 480.00 |
|
|
| Sub - Total | = | Tk. | 12,414.49 |
|
| Incidental charges | 10.00% | = | Tk. | 1,241.45 |
|
| Profit | 10.00% | = | Tk. | 1,241.45 |
|
| Overhead | 3.50% | = | Tk. | 43.45 |
|
|
| Total | = | Tk. | 14,940.84 |
Add VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 953.67 | |
|
|
| Grand Total | = | Tk. | 15,894.51 |
|
|
| Rate per rft | = | Tk. | 158.95 |
|
|
| Rate per rm | = | Tk. | 521.51 |
| Say, | Tk. 522 | .00 per meter |
|
|
|
|
|
|
|
|
|
|
Item No.- 28.2 |
|
|
|
|
|
|
Sand filling the trench with sand of F.M. 0.8 |
|
|
|
|
|
|
Considering: 100'-0" x 1'-6" x 1'-0"= 150 cft
& compaction etc. 1.00 no | @ @ | Tk. 900.00 Tk. 320.00 | per % cft | = = | Tk. Tk. | 1,755.00 320.00 |