SL | Items | Rate | Unit |
1433 | Arsenic (As) | Tk. 1,700.00 | per test |
1434 | Turbidity | Tk. 400.00 | per test |
1435 | Sieve analysis for sand from different layer | Tk. 1,200.00 | per test |
C22 | SUB-SOIL INVESTIGATION WORK |
|
|
| I. Operational cost |
|
|
1436 | Truck fare within 20 km including loading & un-loading | Tk. 1,700.00 | per trip |
1437 | Temporary camp at site for soil investigation work | Tk. 1,053.00 | per site |
1438 | Field Engineer including site allowances: 1-3yrs Exp, Membersip with IEB | Tk. 1,800.00 | per day |
1439 | Foundation Engineer: 5-10yrs exp , Membership with IEB | Tk. 2,500.00 | per day |
1440 | Foreman including site allowances | Tk. 800.00 | per day |
1441 | Rig operators including site allowances | Tk. 600.00 | per day |
1442 | Helper to rig operator/c site allowances | Tk. 390.00 | per day |
1443 | Unskilled labour including site allowances | Tk. 320.00 | per day |
1444 | Asstt laboratory technician | Tk. 800.00 | per day |
1445 | Laboratory technician | Tk. 1,400.00 | per day |
1446 | Laboratory engineer | Tk. 1,800.00 | per day |
1447 | Conveyance within 25 km | Tk. 80.00 | per day |
1448 | Wooden plank (mango) | Tk. 650.00 | per cft |
1449 | Rope | Tk. 60.00 | per kg |
1450 | Small boat | Tk. 700.00 | per day |
1451 | Drum (defects free) | Tk. 1,000.00 | each |
1452 | Hire charge of boring rig | Tk. 3,000.00 | per day |
| II Laboratory Charge for Sub-Soil Investigation Work |
|
|
1453 | Sp. gr. test | Tk. 200.00 | per test |
1454 | Hydrometer, sieve analysis & sp. gr.,& Classification according to ASTM | Tk. 1,200.00 | per test |
1455 | Linear shrinkage | Tk. 700.00 | per test |
1456 | Shrinkage limit | Tk. 500.00 | per test |
1457 | Liquid limit | Tk. 300.00 | per test |