Prev Next


DIVISION 30 : CONCRETE HOLLOW BLOCK, FACINGS AND PAVING STONE, NON FIRE BLOCK

 

 

 

 

 

 

 

 

 

 

Item No.- 30.1

 

 

 

 

 

 

 

 

70 mm thick non-load bearing partition wall with concrete hollow block: cement : lime : sand (1 : 1 : 6)

Consideration 100 sft of work

(a) Material

  1. 70 mm block (390 x 70 x 190 mm)

in/c wastage 116 nos

@

Tk.

 

24.00

per block

=

Tk.

2,784.00

  1. Cement 0.4 bag

@

Tk.

 

395.00

per bag

=

Tk.

158.00

  1. Lime 11.25 kg

@

Tk.

 

20.00

per kg

=

Tk.

225.00

  1. Sand (F.M. 1.2) 3.00 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

42.00

  1. Transportation of block 116 nos

(b) Labour

  1. Head mason 0.1 no

@

@

Tk. Tk.

 

3.66

600.00

each
each

=

=

Tk. Tk.

424.56

60.00

  1. Mason 1 no

@

Tk.

 

500.00

each

=

Tk.

500.00

  1. Ordinary Labour 2.5 nos

@

Tk.

 

320.00

each

=

Tk.

800.00

(c) Scaffolding 25 sft

@

Tk.

 

9.00

per sft

=

Tk.

225.00

(d) Local carriage, curing & sundries etc

 

 

 

 

LS.

=

Tk.

160.00

 

 

 

 

 

Sub - Total

=

Tk.

5,378.56

 

 

 

Profit

10.00%

=

Tk.

537.86

 

 

 

Overhead

3.50%

=

Tk.

188.25

 

 

 

 

 

Total

=

Tk.

6,104.67

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

389.66

 

 

 

 

 

Grand Total

=

Tk.

6,494.33

 

 

 

 

 

Rate per sft

=

Tk.

64.94

30.1.1 Ground floor

 

 

 

 

Rate per sqm

=

Tk.

699.01

 

 

 

 

 

 

 

 

 

Say,

Tk.

 

699 .00 per sqm

 

30.1.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft)

 

 

 

 

per sqm

=

Tk.

31

30.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft)

 

 

 

 

per sqm

=

Tk.

42

30.1.4 Add for each addl floor for 10th floor and above (@ 1.25 nos lab. per

% sft)

 

 

 

per sqm

=

Tk.

52

 

 

 

 

 

 

 

 

 

Item No.- 30.2

 

 

 

 

 

 

 

 

70 mm thick non-load bearing partition wall with concrete hollow block:

 

 

 

 

 

 

 

 

cement : sand (1 : 6) with mortar mix.

 

 

 

 

 

 

 

 

Consideration 100 sft of work

(a) Material

  1. 70 mm block (390 x 70 x 190 mm)

in/c wastage 116 nos

@

Tk.

 

24.00

per block

=

Tk.

2,784.00

  1. Cement 0.5 bag

@

Tk.

 

395.00

per bag

=

Tk.

197.50

  1. Mortar mix 0.015 liter

@

Tk.

 

281.08

per liter

=

Tk.

4.22

  1. Sand (F.M. 1.2) 3.80 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

53.20

  1. Transportation of block 116 nos

(b) Labour

  1. Head mason 0.1 no

@

@

Tk. Tk.

 

3.66

600.00

each
each

=

=

Tk. Tk.

424.56

60.00

  1. Mason 1 no

@

Tk.

 

500.00

each

=

Tk.

500.00

  1. Ordinary Labour 2.5 nos

@

Tk.

 

320.00

each

=

Tk.

800.00

(c) Scaffolding 25 sft

@

Tk.

 

9.00

per sft

=

Tk.

225.00

(d) Local carriage, curing & sundries etc

 

 

 

 

LS.

=

Tk.

160.00

 

 

 

 

 

Sub - Total

=

Tk.

5,208.48

 

 

 

Profit

10.00%

=

Tk.

520.85

 

 

 

Overhead

3.50%

=

Tk.

182.30

 

 

 

 

 

Total

=

Tk.

5,911.63

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

377.34

 

 

 

 

 

Grand Total

=

Tk.

6,288.97

 

 

 

 

 

Rate per sft

=

Tk.

62.89

30.2.1 Ground floor

 

 

 

 

Rate per sqm

=

Tk.

676.95

 

 

 

 

 

 

 

 

 

Say,

Tk.

 

677 .00 per sqm