DIVISION 30 : CONCRETE HOLLOW BLOCK, FACINGS AND PAVING STONE, NON FIRE BLOCK |
| |||||||
|
|
|
|
|
|
|
|
|
Item No.- 30.1 |
|
|
|
|
|
|
|
|
70 mm thick non-load bearing partition wall with concrete hollow block: cement : lime : sand (1 : 1 : 6) Consideration 100 sft of work (a) Material
in/c wastage 116 nos | @ | Tk. |
| 24.00 | per block | = | Tk. | 2,784.00 |
| @ | Tk. |
| 395.00 | per bag | = | Tk. | 158.00 |
| @ | Tk. |
| 20.00 | per kg | = | Tk. | 225.00 |
| @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 42.00 |
(b) Labour
| @ @ | Tk. Tk. |
| 3.66 600.00 | each | = = | Tk. Tk. | 424.56 60.00 |
| @ | Tk. |
| 500.00 | each | = | Tk. | 500.00 |
| @ | Tk. |
| 320.00 | each | = | Tk. | 800.00 |
(c) Scaffolding 25 sft | @ | Tk. |
| 9.00 | per sft | = | Tk. | 225.00 |
(d) Local carriage, curing & sundries etc |
|
|
|
| LS. | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 5,378.56 |
|
|
| Profit | 10.00% | = | Tk. | 537.86 | |
|
|
| Overhead | 3.50% | = | Tk. | 188.25 | |
|
|
|
|
| Total | = | Tk. | 6,104.67 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 389.66 | ||
|
|
|
|
| Grand Total | = | Tk. | 6,494.33 |
|
|
|
|
| Rate per sft | = | Tk. | 64.94 |
30.1.1 Ground floor |
|
|
|
| Rate per sqm | = | Tk. | 699.01 |
|
|
|
|
|
|
|
|
|
Say, | Tk. |
| 699 .00 per sqm |
| ||||
30.1.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft) |
|
|
|
| per sqm | = | Tk. | 31 |
30.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft) |
|
|
|
| per sqm | = | Tk. | 42 |
30.1.4 Add for each addl floor for 10th floor and above (@ 1.25 nos lab. per | % sft) |
|
|
| per sqm | = | Tk. | 52 |
|
|
|
|
|
|
|
|
|
Item No.- 30.2 |
|
|
|
|
|
|
|
|
70 mm thick non-load bearing partition wall with concrete hollow block: |
|
|
|
|
|
|
|
|
cement : sand (1 : 6) with mortar mix. |
|
|
|
|
|
|
|
|
Consideration 100 sft of work (a) Material
in/c wastage 116 nos | @ | Tk. |
| 24.00 | per block | = | Tk. | 2,784.00 |
| @ | Tk. |
| 395.00 | per bag | = | Tk. | 197.50 |
| @ | Tk. |
| 281.08 | per liter | = | Tk. | 4.22 |
| @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 53.20 |
(b) Labour
| @ @ | Tk. Tk. |
| 3.66 600.00 | each | = = | Tk. Tk. | 424.56 60.00 |
| @ | Tk. |
| 500.00 | each | = | Tk. | 500.00 |
| @ | Tk. |
| 320.00 | each | = | Tk. | 800.00 |
(c) Scaffolding 25 sft | @ | Tk. |
| 9.00 | per sft | = | Tk. | 225.00 |
(d) Local carriage, curing & sundries etc |
|
|
|
| LS. | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 5,208.48 |
|
|
| Profit | 10.00% | = | Tk. | 520.85 | |
|
|
| Overhead | 3.50% | = | Tk. | 182.30 | |
|
|
|
|
| Total | = | Tk. | 5,911.63 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 377.34 | ||
|
|
|
|
| Grand Total | = | Tk. | 6,288.97 |
|
|
|
|
| Rate per sft | = | Tk. | 62.89 |
30.2.1 Ground floor |
|
|
|
| Rate per sqm | = | Tk. | 676.95 |
|
|
|
|
|
|
|
|
|
Say, | Tk. |
| 677 .00 per sqm |
| ||||