30.4.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft) | % sft) |
|
|
| per sqm | = = = | Tk. | 31 42 52 |
30.4.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft) | ||||||||
30.4.4 Add for each addl floor for 10th floor and above (@ 1.25 nos lab. per | ||||||||
|
|
|
|
|
|
|
|
|
Item No.- 30.5 |
|
|
|
|
|
|
|
|
140 mm thick non-load bearing external wall with concrete hollow block: |
|
|
|
|
|
|
|
|
cement : lime : sand (1 : 1 : 6) |
|
|
|
|
|
|
|
|
Consideration 100 sft of work (a) Material
in/c wastage 116 nos | @ | Tk. |
| 53.00 | per block | = | Tk. | 6,148.00 |
| @ | Tk. |
| 395.00 | per bag | = | Tk. | 276.50 |
| @ | Tk. |
| 20.00 | per kg | = | Tk. | 300.00 |
| @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 61.60 |
(b) Labour
| @ @ | Tk. Tk. |
| 7.87 600.00 | each | = = | Tk. Tk. | 912.92 60.00 |
| @ | Tk. |
| 500.00 | each | = | Tk. | 750.00 |
| @ | Tk. |
| 320.00 | each | = | Tk. | 1,040.00 |
(c) Scaffolding 25 sft | @ | Tk. |
| 9.00 | per sft | = | Tk. | 225.00 |
(d) Local carriage, curing & sundries etc |
|
|
|
| LS. | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 9,934.02 |
|
|
| Profit | 10.00% | = | Tk. | 993.40 | |
|
|
| Overhead | 3.50% | = | Tk. | 347.69 | |
|
|
|
|
| Total | = | Tk. | 11,275.11 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 719.69 | ||
|
|
|
|
| Grand Total | = | Tk. | 11,994.80 |
|
|
|
|
| Rate per sft | = | Tk. | 119.95 |
30.5.1 Ground floor |
|
|
|
| Rate per sqm | = | Tk. | 1,291.14 |
|
|
|
|
|
|
|
|
|
Say, | Tk. |
| 1,291 .00 per sqm |
| ||||
30.5.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) |
|
|
|
| per sqm | = | Tk. | 42 |
30.5.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % | sft) |
|
|
| per sqm | = | Tk. | 52 |
30.5.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % | sft) |
|
|
| per sqm | = | Tk. | 62 |
|
|
|
|
|
|
|
|
|
Item No.- 30.6 |
|
|
|
|
|
|
|
|
140 mm thick non-load bearing external wall with concrete hollow block: |
|
|
|
|
|
|
|
|
cement : sand (1 : 6) with mortar mix. |
|
|
|
|
|
|
|
|
Consideration 100 sft of work (a) Material
in/c wastage 116 nos | @ | Tk. |
| 53.00 | per block | = | Tk. | 6,148.00 |
| @ | Tk. |
| 395.00 | per bag | = | Tk. | 316.00 |
| @ | Tk. |
| 281.08 | per liter | = | Tk. | 6.75 |
| @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 84.00 |
(iv) Transportation of block 116 nos (b) Labour
| @ @ | Tk. Tk. |
| 7.87 600.00 | each | = = | Tk. Tk. | 912.92 60.00 |
| @ | Tk. |
| 500.00 | each | = | Tk. | 750.00 |
| @ | Tk. |
| 320.00 | each | = | Tk. | 1,040.00 |
(c) Scaffolding 25 sft | @ | Tk. |
| 9.00 | per sft | = | Tk. | 225.00 |
(d) Local carriage, curing & sundries etc. |
|
|
|
| LS. | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 9,702.67 |
|
|
| Profit | 10.00% | = | Tk. | 970.27 | |
|
|
| Overhead | 3.50% | = | Tk. | 339.59 | |
|
|
|
|
| Total | = | Tk. | 11,012.53 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 702.93 | ||
|
|
|
|
| Grand Total | = | Tk. | 11,715.46 |
|
|
|
|
| Rate per sft | = | Tk. | 117.15 |
30.6.1 Ground floor |
|
|
|
| Rate per sqm | = | Tk. | 1,261.00 |
|
|
|
|
|
|
|
|
|
Say, | Tk. |
| 1,261 .00 per sqm |
| ||||