Prev Next
īģŋ

30.4.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft)

% sft)

 

 

 

per sqm
per sqm
per sqm

=

=

=

Tk.
Tk.
Tk.

31

42

52

30.4.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft)

30.4.4 Add for each addl floor for 10th floor and above (@ 1.25 nos lab. per

 

 

 

 

 

 

 

 

 

Item No.- 30.5

 

 

 

 

 

 

 

 

140 mm thick non-load bearing external wall with concrete hollow block:

 

 

 

 

 

 

 

 

cement : lime : sand (1 : 1 : 6)

 

 

 

 

 

 

 

 

Consideration 100 sft of work

(a) Material

  1. 140 mm block (390 x 140 x 190 mm)

in/c wastage 116 nos

@

Tk.

 

53.00

per block

=

Tk.

6,148.00

  1. Cement 0.7 bag

@

Tk.

 

395.00

per bag

=

Tk.

276.50

  1. Lime 15 kg

@

Tk.

 

20.00

per kg

=

Tk.

300.00

  1. Sand (F.M. 1.2) 4.40 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

61.60

  1. Transportation of block 116 nos

(b) Labour

  1. Head mason 0.1 no

@

@

Tk. Tk.

 

7.87

600.00

each
each

=

=

Tk. Tk.

912.92

60.00

  1. Mason 1.5 nos

@

Tk.

 

500.00

each

=

Tk.

750.00

  1. Ordinary Labour 3.25 nos

@

Tk.

 

320.00

each

=

Tk.

1,040.00

(c) Scaffolding 25 sft

@

Tk.

 

9.00

per sft

=

Tk.

225.00

(d) Local carriage, curing & sundries etc

 

 

 

 

LS.

=

Tk.

160.00

 

 

 

 

 

Sub - Total

=

Tk.

9,934.02

 

 

 

Profit

10.00%

=

Tk.

993.40

 

 

 

Overhead

3.50%

=

Tk.

347.69

 

 

 

 

 

Total

=

Tk.

11,275.11

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

719.69

 

 

 

 

 

Grand Total

=

Tk.

11,994.80

 

 

 

 

 

Rate per sft

=

Tk.

119.95

30.5.1 Ground floor

 

 

 

 

Rate per sqm

=

Tk.

1,291.14

 

 

 

 

 

 

 

 

 

Say,

Tk.

 

1,291 .00 per sqm

 

30.5.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft)

 

 

 

 

per sqm

=

Tk.

42

30.5.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per %

sft)

 

 

 

per sqm

=

Tk.

52

30.5.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per %

sft)

 

 

 

per sqm

=

Tk.

62

 

 

 

 

 

 

 

 

 

Item No.- 30.6

 

 

 

 

 

 

 

 

140 mm thick non-load bearing external wall with concrete hollow block:

 

 

 

 

 

 

 

 

cement : sand (1 : 6) with mortar mix.

 

 

 

 

 

 

 

 

Consideration 100 sft of work

(a) Material

  1. 140 mm block (390 x 140 x 190 mm)

in/c wastage 116 nos

@

Tk.

 

53.00

per block

=

Tk.

6,148.00

  1. Cement 0.8 bag

@

Tk.

 

395.00

per bag

=

Tk.

316.00

  1. Mortar mix 0.024 liter

@

Tk.

 

281.08

per liter

=

Tk.

6.75

  1. Sand (F.M. 1.2) 6.00 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

84.00

(iv) Transportation of block 116 nos

(b) Labour

  1. Head mason 0.1 no

@

@

Tk. Tk.

 

7.87

600.00

each
each

=

=

Tk. Tk.

912.92

60.00

  1. Mason 1.5 nos

@

Tk.

 

500.00

each

=

Tk.

750.00

  1. Ordinary Labour 3.25 nos

@

Tk.

 

320.00

each

=

Tk.

1,040.00

(c) Scaffolding 25 sft

@

Tk.

 

9.00

per sft

=

Tk.

225.00

(d) Local carriage, curing & sundries etc.

 

 

 

 

LS.

=

Tk.

160.00

 

 

 

 

 

Sub - Total

=

Tk.

9,702.67

 

 

 

Profit

10.00%

=

Tk.

970.27

 

 

 

Overhead

3.50%

=

Tk.

339.59

 

 

 

 

 

Total

=

Tk.

11,012.53

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

702.93

 

 

 

 

 

Grand Total

=

Tk.

11,715.46

 

 

 

 

 

Rate per sft

=

Tk.

117.15

30.6.1 Ground floor

 

 

 

 

Rate per sqm

=

Tk.

1,261.00

 

 

 

 

 

 

 

 

 

Say,

Tk.

 

1,261 .00 per sqm