30.6.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) | sft) sft) |
|
|
| per sqm | = = = | Tk. | 42 52 62 |
30.6.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % | ||||||||
30.6.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % | ||||||||
|
|
|
|
|
|
|
|
|
Item No.- 30.7 |
|
|
|
|
|
|
|
|
140 mm thick load bearing wall with concrete hollow block: |
|
|
|
|
|
|
|
|
cement : lime : sand (1 : 1 : 6) |
|
|
|
|
|
|
|
|
Consideration 100 sft of work (a) Material
in/c wastage 116 nos | @ | Tk. |
| 56.06 | per block | = | Tk. | 6,502.96 |
| @ | Tk. |
| 395.00 | per bag | = | Tk. | 276.50 |
| @ | Tk. |
| 20.00 | per kg | = | Tk. | 300.00 |
| @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 61.60 |
(b) Labour
| @ @ | Tk. Tk. |
| 7.87 600.00 | each | = = | Tk. Tk. | 912.92 60.00 |
| @ | Tk. |
| 500.00 | each | = | Tk. | 750.00 |
| @ | Tk. |
| 320.00 | each | = | Tk. | 1,040.00 |
(c) Scaffolding 25 sft | @ | Tk. |
| 9.00 | per sft | = | Tk. | 225.00 |
(d) Local carriage, curing & sundries etc. |
|
|
|
| LS. | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 10,288.98 |
|
|
| Profit | 10.00% | = | Tk. | 1,028.90 | |
|
|
| Overhead | 3.50% | = | Tk. | 360.11 | |
|
|
|
|
| Total | = | Tk. | 11,677.99 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 745.40 | ||
|
|
|
|
| Grand Total | = | Tk. | 12,423.39 |
|
|
|
|
| Rate per sft | = | Tk. | 124.23 |
30.7.1 Ground floor |
|
|
|
| Rate per sqm | = | Tk. | 1,337.21 |
|
|
|
|
|
|
|
|
|
Say, | Tk. |
| 1,337 .00 per sqm |
| ||||
30.7.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) |
|
|
|
| per sqm | = | Tk. | 42 |
30.7.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % | sft) |
|
|
| per sqm | = | Tk. | 52 |
30.7.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % | sft) |
|
|
| per sqm | = | Tk. | 62 |
|
|
|
|
|
|
|
|
|
Item No.- 30.8 |
|
|
|
|
|
|
|
|
140 mm thick load bearing wall with concrete hollow block: |
|
|
|
|
|
|
|
|
cement : sand (1 : 6) with mortar mix. |
|
|
|
|
|
|
|
|
Consideration of 100 sft of work (a) Material
in/c wastage 116 nos | @ | Tk. |
| 56.06 | per block | = | Tk. | 6,502.96 |
| @ | Tk. |
| 395.00 | per bag | = | Tk. | 316.00 |
| @ | Tk. |
| 281.08 | per liter | = | Tk. | 6.75 |
| @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 84.00 |
(b) Labour
| @ @ | Tk. Tk. |
| 7.87 600.00 | each | = = | Tk. Tk. | 912.92 60.00 |
| @ | Tk. |
| 500.00 | each | = | Tk. | 750.00 |
| @ | Tk. |
| 320.00 | each | = | Tk. | 1,040.00 |
(c) Scaffolding 25 sft | @ | Tk. |
| 9.00 | per sft | = | Tk. | 225.00 |
(d) Local carriage, curing & sundries etc. |
|
|
|
| LS. | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 10,057.63 |
|
|
| Profit | 10.00% | = | Tk. | 1,005.76 | |
|
|
| Overhead | 3.50% | = | Tk. | 352.02 | |
|
|
|
|
| Total | = | Tk. | 11,415.41 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 728.64 | ||
|
|
|
|
| Grand Total | = | Tk. | 12,144.05 |
|
|
|
|
| Rate per sft | = | Tk. | 121.44 |
30.8.1 Ground floor |
|
|
|
| Rate per sqm | = | Tk. | 1,307.18 |
|
|
|
|
|
|
|
|
|
Say, | Tk. |
| 1,307 .00 per sqm |
| ||||