NEED4ENGINEER.COM , ২০১১ সাল থেকে অলাভজনক ভাবে নির্মাণ কাজের বিভিন্ন বিষয় নিয়ে সেবা দিয়ে যাচ্ছে। এ্যাড না দেখতে লগিন করুন
Prev Next


30.8.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft)

sft) sft)

 

 

 

per sqm
per sqm
per sqm

=

=

=

Tk.
Tk.
Tk.

42

52

62

30.8.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per %

30.8.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per %

 

 

 

 

 

 

 

 

 

Item No.- 30.9

 

 

 

 

 

 

 

 

190 mm thick load bearing wall with concrete hollow block:

 

 

 

 

 

 

 

 

cement : lime : sand (1 : 1 : 6)

 

 

 

 

 

 

 

 

Consideration of 100 sft of work

(a) Material

  1. 190 mm block (390 x 190 x 190 mm)

in/c wastage 116 nos

@

Tk.

 

60.00

per block

=

Tk.

6,960.00

  1. Cement 0.75 bag

@

Tk.

 

395.00

per bag

=

Tk.

296.25

  1. Lime 15 kg

@

Tk.

 

20.00

per kg

=

Tk.

300.00

  1. Sand (F.M. 1.2) 4.70 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

65.80

  1. Transportation of block 116 nos

(b) Labour

  1. Head mason 0.1 no

@

@

Tk. Tk.

 

7.87

600.00

each
each

=

=

Tk. Tk.

912.92

60.00

  1. Mason 1.5 nos

@

Tk.

 

500.00

each

=

Tk.

750.00

  1. Ordinary Labour 3.5 nos

@

Tk.

 

320.00

each

=

Tk.

1,120.00

(c) Scaffolding 25 sft

@

Tk.

 

9.00

per sft

=

Tk.

225.00

(d) Local carriage, curing & sundries etc.

 

 

 

 

LS.

=

Tk.

160.00

 

 

 

 

 

Sub - Total

=

Tk.

10,849.97

 

 

 

Profit

10.00%

=

Tk.

1,085.00

 

 

 

Overhead

3.50%

=

Tk.

379.75

 

 

 

 

 

Total

=

Tk.

12,314.72

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

786.05

 

 

 

 

 

Grand Total

=

Tk.

13,100.77

 

 

 

 

 

Rate per sft

=

Tk.

131.01

30.9.1 Ground floor

 

 

 

 

Rate per sqm

=

Tk.

1,410.19

 

 

 

 

 

 

 

 

 

Say,

Tk.

 

1,410 .00 per sqm

 

30.9.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft)

 

 

 

 

per sqm

=

Tk.

52

30.9.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per %

sft)

 

 

 

per sqm

=

Tk.

62

30.9.4 Add for each addl floor for 10th floor and above (@ 1.75 nos lab. per

% sft)

 

 

 

per sqm

=

Tk.

73

 

 

 

 

 

 

 

 

 

Item No.- 30.10

 

 

 

 

 

 

 

 

190 mm thick load bearing wall with concrete hollow block:

 

 

 

 

 

 

 

 

cement : sand (1 : 6) with mortar mix.

 

 

 

 

 

 

 

 

Consideration of 100 sft of work

(a) Material

  1. 190 mm block (390 x 190 x 190 mm)

in/c wastage 116 nos

@

Tk.

 

60.00

per block

=

Tk.

6,960.00

  1. Cement 0.85 bag

@

Tk.

 

395.00

per bag

=

Tk.

335.75

  1. Mortar mix 0.026 liter

@

Tk.

 

281.08

per liter

=

Tk.

7.31

  1. Sand (F.M. 1.2) 7.00 cft

@

Tk.

 

1,400.00

per % cft

=

Tk.

98.00

  1. Transportation of block 116 nos

(b) Labour

  1. Head mason 0.1 no

@

@

Tk. Tk.

 

7.87

600.00

each
each

=

=

Tk. Tk.

912.92

60.00

  1. Mason 1.5 nos

@

Tk.

 

500.00

each

=

Tk.

750.00

  1. Ordinary Labour 3.5 nos

@

Tk.

 

320.00

each

=

Tk.

1,120.00

(c) Scaffolding 25 sft

@

Tk.

 

9.00

per sft

=

Tk.

225.00

(d) Local carriage, curing & sundries etc.

 

 

 

 

LS.

=

Tk.

160.00

 

 

 

 

 

Sub - Total

=

Tk.

10,628.98

 

 

 

Profit

10.00%

=

Tk.

1,062.90

 

 

 

Overhead

3.50%

=

Tk.

372.01

 

 

 

 

 

Total

=

Tk.

12,063.89

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

770.04

 

 

 

 

 

Grand Total

=

Tk.

12,833.93

30.10.1 Ground floor

 

 

 

 

Rate per sft

=

Tk.

128.34

 

 

 

 

 

Rate per sqm

=

Tk.

1,381.45

 

Say,

Tk.

 

1,381 .00 per sqm