30.8.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) | sft) sft) |
|
|
| per sqm | = = = | Tk. | 42 52 62 |
30.8.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % | ||||||||
30.8.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % | ||||||||
|
|
|
|
|
|
|
|
|
Item No.- 30.9 |
|
|
|
|
|
|
|
|
190 mm thick load bearing wall with concrete hollow block: |
|
|
|
|
|
|
|
|
cement : lime : sand (1 : 1 : 6) |
|
|
|
|
|
|
|
|
Consideration of 100 sft of work (a) Material
in/c wastage 116 nos | @ | Tk. |
| 60.00 | per block | = | Tk. | 6,960.00 |
| @ | Tk. |
| 395.00 | per bag | = | Tk. | 296.25 |
| @ | Tk. |
| 20.00 | per kg | = | Tk. | 300.00 |
| @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 65.80 |
(b) Labour
| @ @ | Tk. Tk. |
| 7.87 600.00 | each | = = | Tk. Tk. | 912.92 60.00 |
| @ | Tk. |
| 500.00 | each | = | Tk. | 750.00 |
| @ | Tk. |
| 320.00 | each | = | Tk. | 1,120.00 |
(c) Scaffolding 25 sft | @ | Tk. |
| 9.00 | per sft | = | Tk. | 225.00 |
(d) Local carriage, curing & sundries etc. |
|
|
|
| LS. | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 10,849.97 |
|
|
| Profit | 10.00% | = | Tk. | 1,085.00 | |
|
|
| Overhead | 3.50% | = | Tk. | 379.75 | |
|
|
|
|
| Total | = | Tk. | 12,314.72 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 786.05 | ||
|
|
|
|
| Grand Total | = | Tk. | 13,100.77 |
|
|
|
|
| Rate per sft | = | Tk. | 131.01 |
30.9.1 Ground floor |
|
|
|
| Rate per sqm | = | Tk. | 1,410.19 |
|
|
|
|
|
|
|
|
|
Say, | Tk. |
| 1,410 .00 per sqm |
| ||||
30.9.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft) |
|
|
|
| per sqm | = | Tk. | 52 |
30.9.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % | sft) |
|
|
| per sqm | = | Tk. | 62 |
30.9.4 Add for each addl floor for 10th floor and above (@ 1.75 nos lab. per | % sft) |
|
|
| per sqm | = | Tk. | 73 |
|
|
|
|
|
|
|
|
|
Item No.- 30.10 |
|
|
|
|
|
|
|
|
190 mm thick load bearing wall with concrete hollow block: |
|
|
|
|
|
|
|
|
cement : sand (1 : 6) with mortar mix. |
|
|
|
|
|
|
|
|
Consideration of 100 sft of work (a) Material
in/c wastage 116 nos | @ | Tk. |
| 60.00 | per block | = | Tk. | 6,960.00 |
| @ | Tk. |
| 395.00 | per bag | = | Tk. | 335.75 |
| @ | Tk. |
| 281.08 | per liter | = | Tk. | 7.31 |
| @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 98.00 |
(b) Labour
| @ @ | Tk. Tk. |
| 7.87 600.00 | each | = = | Tk. Tk. | 912.92 60.00 |
| @ | Tk. |
| 500.00 | each | = | Tk. | 750.00 |
| @ | Tk. |
| 320.00 | each | = | Tk. | 1,120.00 |
(c) Scaffolding 25 sft | @ | Tk. |
| 9.00 | per sft | = | Tk. | 225.00 |
(d) Local carriage, curing & sundries etc. |
|
|
|
| LS. | = | Tk. | 160.00 |
|
|
|
|
| Sub - Total | = | Tk. | 10,628.98 |
|
|
| Profit | 10.00% | = | Tk. | 1,062.90 | |
|
|
| Overhead | 3.50% | = | Tk. | 372.01 | |
|
|
|
|
| Total | = | Tk. | 12,063.89 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 770.04 | ||
|
|
|
|
| Grand Total | = | Tk. | 12,833.93 |
30.10.1 Ground floor |
|
|
|
| Rate per sft | = | Tk. | 128.34 |
|
|
|
|
| Rate per sqm | = | Tk. | 1,381.45 |
| Say, | Tk. |
| 1,381 .00 per sqm |
|
|
|