Prev Next
īģŋ

30.10.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft)

per sqm
per sqm
per sqm

=

=

=

Tk.
Tk.
Tk.

52

62

73

30.10.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft)

30.10.4 Add for each addl floor for 10th floor and above (@ 1.75 nos lab. per % sft)

 

Item No.30.11.1

 

 

 

 

Sand Cement Hollow Block (SCHB) for Internal Wall

 

 

 

 

Considering 100 sft of work

 

 

 

 

1 400x200x100 sand Cement Hollow Block 103 pcs @ Tk. 28.00

per pcs

=

Tk.

2,884.00

2 (SCHB)

Fine Sand (F.M. 1.2) 5 cft @ Tk. 14.00

per cft

=

Tk.

70.00

3 Cement 0.8 bag @ Tk. 415.00

per bag

=

Tk.

332.00

4 Head Mason 0.1 no @ Tk. 600.00

each

=

Tk.

60.00

5 Mason 1 no @ Tk. 500.00

each

=

Tk.

500.00

6 Skilled Labour 2.5 nos @ Tk. 390.00

each

=

Tk.

975.00

7 Scaffolding & Staging 25 sft @ Tk. 20.00

sft

=

Tk.

500.00

8 Ordinary Labour for 7 days curing & 1/8 0.875 no @ Tk. 320.00

each

=

Tk.

280.00

labour par day 0.2 no @ Tk. 320.00

9 Local cariages, storage & sundries etc. (1/5

each

=

Tk.

64.00

 

Sub - Total

=

Tk.

5,665.00

Profit

10.00%

=

Tk.

566.50

Overhead

3.50%

=

Tk.

198.28

 

Total

=

Tk.

6,429.78

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

410.41

 

Grand Total

=

Tk.

6,840.19

30.11.1 Ground floor

Rate per sft

=

Tk.

68.40

 

Rate per sqm

=

Tk.

736.26

Say, Tk. 736 .00 per sqm

 

 

 

30.11.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft)

per sqm

=

Tk.

25.00

30.11.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft)

per sqm

=

Tk.

37.00

30.11.4 Add for each addl floor for 10th floor and above (@ 1.75 nos lab. per % sft)

per sqm

=

Tk.

45.00

 

 

 

 

 

Item No.- 30.12

 

 

 

 

Supplying, carrying and placing of 150 mm concrete ceiling block on perfectly leveled shutter as per direction of the engineer-in-charge.

 

 

 

 

Consideration of 100 nos

(a) Material

  1. 150 mm ceiling block

(600 x 200 x 150 mm) 102 nos @ Tk. 64.87

per block

=

Tk.

6,616.74

  1. Transportation of block 102 nos @ Tk. 8.74

(b) Ordinary Labour

  1. Lifting & placing on shutter 102 nos @ Tk. 8.00

each
each

=

=

Tk. Tk.

891.48

816.00

  1. Local carriage, sundries etc. 102 nos @ Tk. 3.20

each

=

Tk.

326.40

 

Sub - Total

=

Tk.

8,650.62

Profit

10.00%

=

Tk.

865.06

Overhead

3.50%

=

Tk.

302.77

 

Total

=

Tk.

9,818.45

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

626.71

 

Grand Total

=

Tk.

10,445.16

30.12.1 Ground floor

Rate each.

=

Tk.

104.45

 

 

 

 

 

Say, Tk. 104 .00 each

 

30.12.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % pc.)

each

=

Tk.

4

30.12.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % pc.)

each

=

Tk.

5

30.12.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % pcs)

each

=

Tk.

6

 

 

 

 

 

Item No.- 30.13

 

 

 

 

Supplying, carrying and placing of 200 mm concrete ceiling block on perfectly leveled shutter as per direction of the engineer-in-charge.

 

 

 

 

Consideration of 100 nos

(a) Material