30.10.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft) | per sqm | = = = | Tk. | 52 62 73 |
30.10.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft) | ||||
30.10.4 Add for each addl floor for 10th floor and above (@ 1.75 nos lab. per % sft) | ||||
| ||||
Item No.30.11.1 |
|
|
|
|
Sand Cement Hollow Block (SCHB) for Internal Wall |
|
|
|
|
Considering 100 sft of work |
|
|
|
|
1 400x200x100 sand Cement Hollow Block 103 pcs @ Tk. 28.00 | per pcs | = | Tk. | 2,884.00 |
2 (SCHB) Fine Sand (F.M. 1.2) 5 cft @ Tk. 14.00 | per cft | = | Tk. | 70.00 |
3 Cement 0.8 bag @ Tk. 415.00 | per bag | = | Tk. | 332.00 |
4 Head Mason 0.1 no @ Tk. 600.00 | each | = | Tk. | 60.00 |
5 Mason 1 no @ Tk. 500.00 | each | = | Tk. | 500.00 |
6 Skilled Labour 2.5 nos @ Tk. 390.00 | each | = | Tk. | 975.00 |
7 Scaffolding & Staging 25 sft @ Tk. 20.00 | sft | = | Tk. | 500.00 |
8 Ordinary Labour for 7 days curing & 1/8 0.875 no @ Tk. 320.00 | each | = | Tk. | 280.00 |
labour par day 0.2 no @ Tk. 320.00 9 Local cariages, storage & sundries etc. (1/5 | each | = | Tk. | 64.00 |
| Sub - Total | = | Tk. | 5,665.00 |
Profit | 10.00% | = | Tk. | 566.50 |
Overhead | 3.50% | = | Tk. | 198.28 |
| Total | = | Tk. | 6,429.78 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 410.41 |
| Grand Total | = | Tk. | 6,840.19 |
30.11.1 Ground floor | Rate per sft | = | Tk. | 68.40 |
| Rate per sqm | = | Tk. | 736.26 |
Say, Tk. 736 .00 per sqm |
|
|
| |
30.11.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft) | per sqm | = | Tk. | 25.00 |
30.11.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft) | per sqm | = | Tk. | 37.00 |
30.11.4 Add for each addl floor for 10th floor and above (@ 1.75 nos lab. per % sft) | per sqm | = | Tk. | 45.00 |
|
|
|
|
|
Item No.- 30.12 |
|
|
|
|
Supplying, carrying and placing of 150 mm concrete ceiling block on perfectly leveled shutter as per direction of the engineer-in-charge. |
|
|
|
|
Consideration of 100 nos (a) Material
(600 x 200 x 150 mm) 102 nos @ Tk. 64.87 | per block | = | Tk. | 6,616.74 |
(b) Ordinary Labour
| each | = = | Tk. Tk. | 891.48 816.00 |
| each | = | Tk. | 326.40 |
| Sub - Total | = | Tk. | 8,650.62 |
Profit | 10.00% | = | Tk. | 865.06 |
Overhead | 3.50% | = | Tk. | 302.77 |
| Total | = | Tk. | 9,818.45 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 626.71 |
| Grand Total | = | Tk. | 10,445.16 |
30.12.1 Ground floor | Rate each. | = | Tk. | 104.45 |
|
|
|
|
|
Say, Tk. 104 .00 each |
| |||
30.12.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % pc.) | each | = | Tk. | 4 |
30.12.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % pc.) | each | = | Tk. | 5 |
30.12.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % pcs) | each | = | Tk. | 6 |
|
|
|
|
|
Item No.- 30.13 |
|
|
|
|
Supplying, carrying and placing of 200 mm concrete ceiling block on perfectly leveled shutter as per direction of the engineer-in-charge. |
|
|
|
|
Consideration of 100 nos (a) Material |
|
|
|
|