Prev Next


 

Item No.- 30.20.1

 

 

 

 

 

225 mm thick wall with concrete solid block (215 x 100 x 65) mm with cement mortar (1:6) Consideration of 100 sft of work

(a) Materials

  1. Solid bloc for 225 mm

thick wall in/c wastage 1110 nos @ Tk.

14.00

each

=

Tk.

15,540.00

  1. Cement 3.00 bags @ Tk.

395.00

per bag

=

Tk.

1,185.00

  1. Sand 22.5 cft @ Tk.

1,400.00

per % cft

=

Tk.

315.00

  1. Transportation 1110 nos @ Tk.

(b) Labour

  1. block work in/c screening sand 100 sft @ Tk.

1.64

15.26

each
per sft

=

=

Tk. Tk.

1,820.40

1,526.00

  1. Scaffolding 25 sft @ Tk.

9.00

per sft

=

Tk.

225.00

  1. Labour for local carriage and sundries etc. 0.5 no @ Tk.

320.00

each

=

Tk.

160.00

 

 

Sub - Total

=

Tk.

20,771.40

 

Profit

10.00%

=

Tk.

2,077.14

 

Overhead

3.50%

=

Tk.

727.00

 

 

Total

=

Tk.

23,575.54

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

1,504.82

 

 

Grand Total

=

Tk.

25,080.36

 

 

Rate per sft

=

Tk.

250.80

30.20.1.1 Ground floor

 

Rate per sqm

=

Tk.

2,699.61

 

 

 

 

 

 

Say, Tk.

2,700 .00 per sqm

 

30.20.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft)

 

per sqm

=

Tk.

42

30.20.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft)

 

per sqm

=

Tk.

52

30.20.1.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft)

 

per sqm

=

Tk.

62

 

 

 

 

 

 

Item No.- 30.20.2

 

 

 

 

 

112 mm thick wall with concrete solid block (215 x 100 x 65) mm with cement mortar (1:6)

 

 

 

 

 

Consideration of 100 sft work

(a) Materials

  1. Solid bloc for 112 mm

thick wall in/c wastage 560 nos @ Tk.

14.00

each

=

Tk.

7,840.00

  1. Cement 1.00 bag @ Tk.

395.00

per bag

=

Tk.

395.00

  1. Sand 7.5 cft @ Tk.

1,400.00

per % cft

=

Tk.

105.00

  1. Transportation 560 nos @ Tk.

(b) Labour

  1. Block work in/c screening sand & curing 100 sft @ Tk.

1.64

10.14

each
per sft

=

=

Tk. Tk.

918.40

1,014.00

  1. Scaffolding 25 sft @ Tk.

9.00

per sft

=

Tk.

225.00

  1. Labour for local carriage, sundries etc. 0.5 no @ Tk.

320.00

each

=

Tk.

160.00

 

 

Sub - Total

=

Tk.

10,657.40

 

Profit

10.00%

=

Tk.

1,065.74

 

Overhead

3.50%

=

Tk.

373.01

 

 

Total

=

Tk.

12,096.15

Add VAT with adjustment factor

1.06383

6.00%

=

Tk.

772.09

 

 

Grand Total

=

Tk.

12,868.24

 

 

Rate per sft

=

Tk.

128.68

30.20.2.1 Ground floor

 

Rate per sqm

=

Tk.

1,385.11

 

 

 

 

 

 

Say, Tk.

1,385 .00 per sqm

 

30.20.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft)

 

per sqm

=

Tk.

42

30.20.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft)

 

per sqm

=

Tk.

52

30.20.2.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft)

 

per sqm

=

Tk.

62

 

 

 

 

 

 

Item No.30.21

 

 

 

 

 

Sand-Cement Solid Block (1:6) Wall

 

 

 

 

 

Considering = 100 sft of work

1 250x115x115 sand cement Solid Block 275 pcs @ Tk.

10.00

per pcs

=

Tk.

2,750.00

2 Sand (F.M. 1.2) 7.50 cft @ Tk.

14.00

per cft

=

Tk.

105.00