3 Cement 1.5 nos @ 4 Head Mason 0 no @ 5 Mason 0.5 no @ 6 Skilled Labour 0.5 no @ 7 Ordinary Labour 0.5 no @ 8 Labour of scanning and washing sand 0.2 no @ 9 Ordinary Labour for 7 days curing @ 1/8 1 no @ 10 Scaffolding & Staging labour per day 25.00 sft @ 11 Local carriages, storage & sundries etc. (1/5 0.2 no @ | Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. | 415.00 600.00 500.00 390.00 320.00 390.00 320.00 20.00 320.00 | Per No. each each each each each each per sft each | = = = = = = = = = | Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. | 622.50 60.00 250.00 195.00 160.00 78.00 280.00 500.00 64.00 |
|
|
| Sub - Total | = | Tk. | 5,064.50 |
|
| Profit | 10.00% | = | Tk. | 506.45 |
|
| Overhead | 3.50% | = | Tk. | 177.26 |
|
|
| Total | = | Tk. | 5,748.21 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 366.91 |
|
|
| Grand Total | = | Tk. | 6,115.12 |
|
|
| Rate per sft | = | Tk. | 61.15 |
30.21.1 Ground floor |
|
| Rate per sqm | = | Tk. | 658.22 |
|
|
|
|
| Tk. | 32.00 |
Say, | Tk. | 658 .00 per sqm |
| |||
30.21.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) |
|
| per sqm | = | ||
30.21.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) |
|
| per sqm | = | Tk. | 40.00 |
30.21.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) |
|
| per sqm | = | Tk. | 50.00 |
|
|
|
|
|
|
|
Item No.- -30.22 |
|
|
|
|
|
|
115mm Thermal block work (1:4) in superstructure |
|
|
|
|
|
|
Considering 100 sft work 1 Thermal Block (Size: 300x115x115) 230 pcs @ | Tk. | 22.00 | per pcs | = | Tk. | 5,060.00 |
2 Sand (F.M. 1.2) 7.50 cft @ | Tk. | 14.00 | per cft | = | Tk. | 105.00 |
3 Cement 1.5 bags @ | Tk. | 415.00 | Par bag | = | Tk. | 622.50 |
4 Head Mason 0 no @ | Tk. | 600.00 | each | = | Tk. | 60.00 |
5 Mason 0.75 no @ | Tk. | 500.00 | each | = | Tk. | 375.00 |
6 Skilled Labour 0.5 no @ | Tk. | 390.00 | each | = | Tk. | 195.00 |
7 Ordinary labour 0.5 no @ | Tk. | 320.00 | each | = | Tk. | 160.00 |
8 Labour for cleaning the Block 0.2 no @ | Tk. | 320.00 | each | = | Tk. | 64.00 |
9 Labour for screening and washing sand 0 no @ | Tk. | 320.00 | each | = | Tk. | 64.00 |
10 Labour for 7 days curing @ 1/8 labour per day 0.88 no @ | Tk. | 320.00 | each | = | Tk. | 280.00 |
11 Scaffolding &Staging 25 sft @ | Tk. | 20.00 | per sft | = | Tk. | 500.00 |
12 Local carriges, storage & sundries etc. (1/2 0.5 no @ | Tk. | 320.00 | each | = | Tk. | 160.00 |
|
|
| Sub - Total | = | Tk. | 7,645.50 |
|
| Profit | 10.00% | = | Tk. | 764.55 |
|
| Overhead | 3.50% | = | Tk. | 267.59 |
|
|
| Total | = | Tk. | 8,677.64 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 553.89 |
|
|
| Grand Total | = | Tk. | 9,231.53 |
|
|
| Rate per sft | = | Tk. | 92.32 |
30.19.2.1 Ground floor |
|
| Rate per sqm | = | Tk. | 993.36 |
|
|
|
|
| Tk. | 18.00 |
Say, | Tk. | 993 .00 per sqm |
| |||
30.22.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) |
|
| per sqm | = | ||
30.22.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) |
|
| per sqm | = | Tk. | 24.00 |
30.22.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) |
|
| per sqm | = | Tk. | 28.00 |
|
|
|
|
|
|
|
Item No.--30.23 |
|
|
|
|
|
|
Compressed Stabilized Earth Block (1:6) (CSEB) Wall |
|
|
|
|
|
|
Considering 100 sft of work 1 240x115x70 CSEB 480 pcs @ | Tk. | 7.00 | per pcs | = | Tk. | 3,360.00 |
2 Sand (F.M. 1.2) 18.00 cft @ | Tk. | 14.00 | per cft | = | Tk. | 252.00 |
3 Cement 1.75 bags @ | Tk. | 415.00 | per bags | = | Tk. | 726.25 |