Prev Next
īģŋ

3 Cement 1.5 nos @

4 Head Mason 0 no @

5 Mason 0.5 no @

6 Skilled Labour 0.5 no @

7 Ordinary Labour 0.5 no @

8 Labour of scanning and washing sand 0.2 no @

9 Ordinary Labour for 7 days curing @ 1/8 1 no @

10 Scaffolding & Staging

labour per day 25.00 sft @

11 Local carriages, storage & sundries etc. (1/5 0.2 no @

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

415.00 600.00 500.00 390.00 320.00 390.00 320.00

20.00

320.00

Per No. each each each each each each per sft each

= = = = = = = = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

622.50 60.00 250.00 195.00 160.00 78.00 280.00 500.00 64.00

 

 

 

Sub - Total

=

Tk.

5,064.50

 

 

Profit

10.00%

=

Tk.

506.45

 

 

Overhead

3.50%

=

Tk.

177.26

 

 

 

Total

=

Tk.

5,748.21

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

366.91

 

 

 

Grand Total

=

Tk.

6,115.12

 

 

 

Rate per sft

=

Tk.

61.15

30.21.1 Ground floor

 

 

Rate per sqm

=

Tk.

658.22

 

 

 

 

 

Tk.

32.00

Say,

Tk.

658 .00 per sqm

 

30.21.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft)

 

 

per sqm

=

30.21.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft)

 

 

per sqm

=

Tk.

40.00

30.21.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft)

 

 

per sqm

=

Tk.

50.00

 

 

 

 

 

 

 

Item No.- -30.22

 

 

 

 

 

 

115mm Thermal block work (1:4) in superstructure

 

 

 

 

 

 

Considering 100 sft work

1 Thermal Block (Size: 300x115x115) 230 pcs @

Tk.

22.00

per pcs

=

Tk.

5,060.00

2 Sand (F.M. 1.2) 7.50 cft @

Tk.

14.00

per cft

=

Tk.

105.00

3 Cement 1.5 bags @

Tk.

415.00

Par bag

=

Tk.

622.50

4 Head Mason 0 no @

Tk.

600.00

each

=

Tk.

60.00

5 Mason 0.75 no @

Tk.

500.00

each

=

Tk.

375.00

6 Skilled Labour 0.5 no @

Tk.

390.00

each

=

Tk.

195.00

7 Ordinary labour 0.5 no @

Tk.

320.00

each

=

Tk.

160.00

8 Labour for cleaning the Block 0.2 no @

Tk.

320.00

each

=

Tk.

64.00

9 Labour for screening and washing sand 0 no @

Tk.

320.00

each

=

Tk.

64.00

10 Labour for 7 days curing @ 1/8 labour per day 0.88 no @

Tk.

320.00

each

=

Tk.

280.00

11 Scaffolding &Staging 25 sft @

Tk.

20.00

per sft

=

Tk.

500.00

12 Local carriges, storage & sundries etc. (1/2 0.5 no @

Tk.

320.00

each

=

Tk.

160.00

 

 

 

Sub - Total

=

Tk.

7,645.50

 

 

Profit

10.00%

=

Tk.

764.55

 

 

Overhead

3.50%

=

Tk.

267.59

 

 

 

Total

=

Tk.

8,677.64

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

553.89

 

 

 

Grand Total

=

Tk.

9,231.53

 

 

 

Rate per sft

=

Tk.

92.32

30.19.2.1 Ground floor

 

 

Rate per sqm

=

Tk.

993.36

 

 

 

 

 

Tk.

18.00

Say,

Tk.

993 .00 per sqm

 

30.22.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft)

 

 

per sqm

=

30.22.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft)

 

 

per sqm

=

Tk.

24.00

30.22.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft)

 

 

per sqm

=

Tk.

28.00

 

 

 

 

 

 

 

Item No.--30.23

 

 

 

 

 

 

Compressed Stabilized Earth Block (1:6) (CSEB) Wall

 

 

 

 

 

 

Considering 100 sft of work

1 240x115x70 CSEB 480 pcs @

Tk.

7.00

per pcs

=

Tk.

3,360.00

2 Sand (F.M. 1.2) 18.00 cft @

Tk.

14.00

per cft

=

Tk.

252.00

3 Cement 1.75 bags @

Tk.

415.00

per bags

=

Tk.

726.25