4 Head Mason 0 no @ 5 Mason 0.5 no @ 6 Skilled Labour 0.5 no @ 7 Ordinary labour 0.2 no @ 8 Labour for Screening & washing sand 0.2 no @ 9 Ordinary Labour for 7 days curing & 1/8 1 no @ labour par day 25.00 sft @ 10 Scaffolding & Staging 11 Local carriages, storage & sundries etc. (1/5 0.2 no @ | Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. | 600.00 500.00 390.00 320.00 320.00 320.00 20.00 320.00 | per no. each each each each each per sft each | = = = = = = = = | Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. | 60.00 250.00 195.00 64.00 64.00 280.00 500.00 64.00 |
|
|
| Sub - Total | = | Tk. | 5,815.25 |
|
| Profit | 10.00% | = | Tk. | 581.53 |
|
| Overhead | 3.50% | = | Tk. | 203.53 |
|
|
| Total | = | Tk. | 6,600.31 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 421.30 |
|
|
| Grand Total | = | Tk. | 7,021.61 |
|
|
| Rate per sft | = | Tk. | 70.22 |
30.23.1 Ground floor |
|
| Rate per sqm | = | Tk. | 755.85 |
|
|
|
|
| Tk. | 30.00 |
Say, | Tk. | 756 .00 per sqm |
| |||
30.23.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) |
|
| per sqm | = | ||
30.23.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) |
|
| per sqm | = | Tk. | 39.00 |
30.23.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) |
|
| per sqm | = | Tk. | 50.00 |
|
|
|
|
|
|
|
Item No.-30.24 |
|
|
|
|
|
|
Soil-Cement Stabilization bed for Floor & Foundation |
|
|
|
|
|
|
Considering = 100.00 sft of work 1 Sand (F.M. 0.8) 44 cft @ | Tk. | 9.00 | per cft | = | Tk. | 396.00 |
2 Cement 4.40 bags @ | Tk. | 415.00 | per bag | = | Tk. | 1,826.00 |
3 Hire charge of Mixture machine including Oil & 0.05perato no @ | Tk. | 2,004.00 | Per day | = | Tk. | 100.20 |
4 Mason 1 no @ | Tk. | 500.00 | each | = | Tk. | 250.00 |
5 Skilled Labour 2 nos @ | Tk. | 390.00 | each | = | Tk. | 780.00 |
6 Local Carriage, Sundries, T & P, water etc. 0.2 no @ | Tk. | 320.00 | each | = | Tk. | 64.00 |
|
|
| Sub - Total | = | Tk. | 3,416.20 |
|
| Profit | 10.00% | = | Tk. | 341.62 |
|
| Overhead | 3.50% | = | Tk. | 119.57 |
|
|
| Total | = | Tk. | 3,877.39 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 247.49 |
|
|
| Grand Total | = | Tk. | 4,124.88 |
|
|
| Rate per sft | = | Tk. | 41.25 |
Ground floor |
|
| Rate per sqm | = | Tk. | 443.85 |
Say, | Tk. | 444 .00 per sqm |
|
|
| |
|
|
|
|
|
|
|
Item No.--30.25 |
|
|
|
|
|
|
Sand Cement Solid Block Soling in Floor/Foundation (SCSB) |
|
|
|
|
|
|
Considering = 100 sft of work |
|
|
|
|
|
|
1 Sand Cement Solid Block (SCSB) (Size: 230 nos @ | Tk. | 11.00 | Per no. | = | Tk. | 2,530.00 |
300x115x70) 5.00 cft @ 2 Sand (F.M = 0.8) | Tk. | 9.00 | per cft | = | Tk. | 45.00 |
3 Mason 0.25 no @ | Tk. | 500.00 | each | = | Tk. | 125.00 |
4 Skilled Labour 1 no @ | Tk. | 390.00 | each | = | Tk. | 390.00 |
5 Local carriages, storage & sundries etc. (1/5 0.2 no @ | Tk. | 320.00 | each | = | Tk. | 64.00 |
|
|
| Sub - Total | = | Tk. | 3,154.00 |
|
| Profit | 10.00% | = | Tk. | 315.40 |
|
| Overhead | 3.50% | = | Tk. | 110.39 |
|
|
| Total | = | Tk. | 3,579.79 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 228.50 |
|
|
| Grand Total | = | Tk. | 3,808.29 |
|
|
| Rate per sft | = | Tk. | 38.08 |
|
|
| Rate per sqm | = | Tk. | 409.74 |
Say, | Tk. | 410 .00 per sqm |
|
|
| |