Item No.- 31.1 |
Mobilization and demobilization of boring equipment and man-power: drilling rig comprising drilling pipe, drop hammer, tripod, pulley, chain, wrange, sample collection devices etc tools and plant; tripol for temporary camp, 8-10 men work-force) Considering 1 No. site
ways) per site = Tk. 1,053.00
(2 x 8 nos) 16 nos @ Tk. 80.00 each = Tk. 1,280.00 (c) Wages for man power
6 nos x (1/2 + 1/2) 6 mandays @ Tk. 390.00 each = Tk. 2,340.00
|
Sub - Total = Tk. 9,684.20 Profit 10.00% = Tk. 968.42 Overhead 3.50% = Tk. 338.95 |
Total = Tk. 10,991.57 Add VAT with adjustment factor 1.06383 6.00% = Tk. 701.59 |
Grand Total = Tk. 11,693.16 Rate per site = Tk. 11,693.16 |
Say, Tk. 11,693 .00 per site |
|
Item No.- 31.2 |
General Sub - Soil investigation by exploratory borings , mobilization ,collection samples testings & reports etc. in numbers as required. a) Boring 100 mm dia bore-hole by wash boring method
(1 x 20% per day x 0.44day) 0.09 manday @ Tk. 800.00 each = Tk. 72.00
(1 x 30% per day x 0.44 day) 0.13 manday @ Tk. 600.00 each = Tk. 78.00
(5 x 50% per day x 0.44 day) 1.10 mandays @ Tk. 390.00 each = Tk. 429.00 |
Sub-Total = Tk. 1,899.00 Rate per meter = Tk. 211.00 b) SPT @ 1.5m interval Considering 6 points SPT execution in 0.4
(1 x 30% per day x 0.44 day) 0.13 manday @ Tk. 800.00 each = Tk. 104.00
(1 x 30% per day x 0.44 day) 0.13 manday @ Tk. 600.00 each = Tk. 78.00
(6 x 30% per day x 0.44) 0.79 manday @ Tk. 390.00 each = Tk. 308.10
|
Sub-Total = Tk. 538.10 Rate per Point = Tk. 89.68 c) Collection of disturbed/ undisturbed samples, visual soil classification & mentioned relevent lab test
|