Item No.- 30.27.3 |
|
|
|
| |
Providing 418 x 330 x 17 mm Antique red colour roof tiles on pre-fabricated truss Consideration of 100 nos (a) Materials
| each | = | Tk. | 5,003.10 | |
| @ Tk. 10.35 | each | = | Tk. | 621.00 |
(b) Labour (i) Lifting & placing on shutter 102 nos | @ Tk. 3.45 @ Tk. 3.20 | each | = = | Tk. Tk. | 351.90 326.40 |
(c) Tools and machinery for 102 nos | @ Tk. 3.20 | per sft |
| Tk. | 326.40 |
|
| Sub - Total | = | Tk. | 6,628.80 |
| Profit | 10.00% | = | Tk. | 662.88 |
| Overhead | 3.50% | = | Tk. | 232.01 |
|
| Total | = | Tk. | 7,523.69 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 480.24 | |
|
| Grand Total | = | Tk. | 8,003.93 |
|
| Rate each. | = | Tk. | 80.04 |
| Say, Tk. 80 .00 each |
|
|
| |
|
|
|
|
|
|
Item No.- 30.27.4 |
|
|
|
|
|
Providing 418 x 330 x 17 mm green colour roof tiles on prefabricated truss |
|
|
|
|
|
Consideration of 100 nos (a) Materials
roof tiles in/c wastag 102 nos | @ Tk. 53.36 | each | = | Tk. | 5,442.72 |
| @ Tk. 10.35 | each | = | Tk. | 621.00 |
(b) Labour (i) Lifting & placing on shutter 100 nos | @ Tk. 3.45 @ Tk. 3.20 | each | = = | Tk. Tk. | 351.90 320.00 |
(c) Tools and machinery for 100 nos | @ Tk. 3.20 | per sft |
| Tk. | 320.00 |
|
| Sub - Total | = | Tk. | 7,055.62 |
| Profit | 10.00% | = | Tk. | 705.56 |
| Overhead | 3.50% | = | Tk. | 246.95 |
|
| Total | = | Tk. | 8,008.13 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 511.16 | |
|
| Grand Total | = | Tk. | 8,519.29 |
|
| Rate each. | = | Tk. | 85.19 |
| Say, Tk. 85 .00 each |
|
|
| |
|
|
|
|
|
|
Item No.- 30.28 |
|
|
|
| |
Supplying and placing of concrete kerb stone (K3) as per direction of the engineer in charge |
|
|
|
| |
Consideration of 100 nos (a) Materials
| each | = | Tk. | 15,000.00 | |
| @ Tk. 395.00 | per bag | = | Tk. | 592.50 |
(b) Labour (i) Local carriage & placing 100 nos | @ Tk. 31.19 @ Tk. 9.60 | each | = = | Tk. Tk. | 3,119.00 960.00 |
|
| Sub - Total | = | Tk. | 19,671.50 |
| Profit | 10.00% | = | Tk. | 1,967.15 |
| Overhead | 3.50% | = | Tk. | 688.50 |
|
| Total | = | Tk. | 22,327.15 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 1,425.14 | |
|
| Grand Total | = | Tk. | 23,752.29 |
|
| Rate each. | = | Tk. | 237.52 |
| Say, Tk. 238 .00 each |
|
|
| |