  1. Brooming, cleaning etc. LS
  2. T & P, sundries etc. LS

=

=

Tk. Tk.

32.00

48.00

SubTotal

Contractor's profit 10%

Overhead expenses 3.50%

=

=

=

Tk.
Tk.
Tk.

435.00

43.50

15.23

Total

=

Tk.

493.73

VAT with adjustment factor 1.06383 6.00%

=

Tk.

31.51

Grand Total

=

Tk.

525.24

Rate per sqm

=

Tk.

52.52

Say, Tk. 53 .00 per sqm

 

 

 

 

 

 

 

Item No. 32.4

 

 

 

Dismantling unserviceable/damaged terraced roof including beam, column, borga & tiles etc.

 

 

 

Considering 10 sqm of works

  1. Skilled labour 1.00 no @ Tk. 390.00 each

=

Tk.

390.00

  1. Ordinary labour 1.00 no @ Tk. 320.00 each

=

Tk.

320.00

  1. Scaffolding 2.50 sqm @ Tk. 96.84 per sqm

=

Tk.

242.10

  1. Brooming, cleaning etc. LS

=

Tk.

32.00

  1. T & P, sundries etc. LS

=

Tk.

160.00

SubTotal

=

Tk.

1,144.10

Contractor's profit 10%

=

Tk.

114.41

Overhead expenses 3.50%

=

Tk.

40.04

Total

=

Tk.

1,298.55

VAT with adjustment factor 1.06383 6.00%

=

Tk.

82.89

Grand Total

=

Tk.

1,381.44

Rate per sqm

=

Tk.

138.14

Say, Tk. 138 .00 per sqm

 

 

 

 

 

 

 

Item No. 32.5.1.1

 

 

 

Dismantling unserviceable/damaged brick works of thickness 250 mm and above in cement or lime in foundation and superstructure

 

 

 

Considering 3 cum of works

  1. Skilled labour 1.25 nos @ Tk. 390.00 each

=

Tk.

487.50

  1. Ordinary labour 1.25 nos @ Tk. 320.00 each

=

Tk.

400.00

  1. Brooming, cleaning etc. LS

=

Tk.

32.00

  1. T & P, scaffolding, ladder, sundries etc. LS

=

Tk.

160.00

SubTotal

=

Tk.

1,079.50

Contractor's profit 10%

=

Tk.

107.95

Overhead expenses 3.50%

=

Tk.

37.78

Total

=

Tk.

1,225.23

VAT with adjustment factor 1.06383 6.00%

=

Tk.

78.21

Grand Total

=

Tk.

1,303.44

Rate per cum

=

Tk.

434.48

Say, Tk. 434 .00 per cum

 

 

 

 

 

 

 

Item No. 32.5.1.2

 

 

 

Dismantling unserviceable/damaged brick works of thickness 75/125 mm in cement or lime in foundation and superstructure

 

 

 

Considering 10 sqm of works

  1. Skilled labour 0.50 nos @ Tk. 390.00 each

=

Tk.

195.00

  1. Ordinary labour 0.50 nos @ Tk. 320.00 each

=

Tk.

160.00

  1. Brooming, cleaning etc. LS

=

Tk.

16.00

  1. T & P, scaffolding, ladder, sundries etc. LS

=

Tk.

64.00

SubTotal

=

Tk.

435.00

Contractor's profit 10%

=

Tk.

43.50