| = = | Tk. Tk. | 32.00 48.00 |
SubTotal Contractor's profit 10% Overhead expenses 3.50% | = = = | Tk. | 435.00 43.50 15.23 |
Total | = | Tk. | 493.73 |
VAT with adjustment factor 1.06383 6.00% | = | Tk. | 31.51 |
Grand Total | = | Tk. | 525.24 |
Rate per sqm | = | Tk. | 52.52 |
Say, Tk. 53 .00 per sqm |
|
|
|
|
|
|
|
Item No. 32.4 |
|
|
|
Dismantling unserviceable/damaged terraced roof including beam, column, borga & tiles etc. |
|
|
|
Considering 10 sqm of works
| = | Tk. | 390.00 |
| = | Tk. | 320.00 |
| = | Tk. | 242.10 |
| = | Tk. | 32.00 |
| = | Tk. | 160.00 |
SubTotal | = | Tk. | 1,144.10 |
Contractor's profit 10% | = | Tk. | 114.41 |
Overhead expenses 3.50% | = | Tk. | 40.04 |
Total | = | Tk. | 1,298.55 |
VAT with adjustment factor 1.06383 6.00% | = | Tk. | 82.89 |
Grand Total | = | Tk. | 1,381.44 |
Rate per sqm | = | Tk. | 138.14 |
Say, Tk. 138 .00 per sqm |
|
|
|
|
|
|
|
Item No. 32.5.1.1 |
|
|
|
Dismantling unserviceable/damaged brick works of thickness 250 mm and above in cement or lime in foundation and superstructure |
|
|
|
Considering 3 cum of works
| = | Tk. | 487.50 |
| = | Tk. | 400.00 |
| = | Tk. | 32.00 |
| = | Tk. | 160.00 |
SubTotal | = | Tk. | 1,079.50 |
Contractor's profit 10% | = | Tk. | 107.95 |
Overhead expenses 3.50% | = | Tk. | 37.78 |
Total | = | Tk. | 1,225.23 |
VAT with adjustment factor 1.06383 6.00% | = | Tk. | 78.21 |
Grand Total | = | Tk. | 1,303.44 |
Rate per cum | = | Tk. | 434.48 |
Say, Tk. 434 .00 per cum |
|
|
|
|
|
|
|
Item No. 32.5.1.2 |
|
|
|
Dismantling unserviceable/damaged brick works of thickness 75/125 mm in cement or lime in foundation and superstructure |
|
|
|
Considering 10 sqm of works
| = | Tk. | 195.00 |
| = | Tk. | 160.00 |
| = | Tk. | 16.00 |
| = | Tk. | 64.00 |
SubTotal | = | Tk. | 435.00 |
Contractor's profit 10% | = | Tk. | 43.50 |