| Contractor's profit Overhead expenses | SubTotal = 10% = 3.50% = | Tk. | 764.40 76.44 26.75 |
Total = | Tk. | 867.59 | ||
VAT with adjustment factor | 1.06383 | 6.00% = | Tk. | 55.38 |
|
| Grand Total = | Tk. | 922.97 |
|
| Rate per sqm = | Tk. | 92.30 |
Say, | Tk. 92 .00 per sqm |
|
| |
|
|
|
|
|
Item No. 32.47.2 |
|
|
|
|
Renewing Interior Premium acrylic emulsion painting (silky finish) : 1 coat |
|
|
|
|
Considering 10 sqm of work for 1 coat
| Tk. 391.00 | per liter = | Tk. | 273.70 |
| Tk. 600.00 | each = | Tk. | 300.00 |
| Tk. 390.00 | each = | Tk. | 195.00 |
|
| LS = | Tk. | 32.00 |
|
| LS = | Tk. | 96.00 |
|
| SubTotal = | Tk. | 896.70 |
| Contractor's profit | 10% = | Tk. | 89.67 |
| Overhead expenses | 3.50% = | Tk. | 31.38 |
|
| Total = | Tk. | 1,017.75 |
VAT with adjustment factor | 1.06383 | 6.00% = | Tk. | 64.96 |
|
| Grand Total = | Tk. | 1,082.71 |
|
| Rate per sqm = | Tk. | 108.27 |
Say, | Tk. 108 .00 per sqm |
|
| |
|
|
|
|
|
Item No. 32.47.3 |
|
|
|
|
Renewing interior super premium acrylic emulsion painting (odorless): 1 coat |
|
|
|
|
Considering 10 sqm of work for 1 coat
| Tk. 500.00 | per liter = | Tk. | 350.00 |
| Tk. 600.00 | each = | Tk. | 300.00 |
| Tk. 390.00 | each = | Tk. | 195.00 |
|
| LS = | Tk. | 32.00 |
|
| LS = | Tk. | 96.00 |
|
| SubTotal = | Tk. | 973.00 |
| Contractor's profit | 10% = | Tk. | 97.30 |
| Overhead expenses | 3.50% = | Tk. | 34.06 |
|
| Total = | Tk. | 1,104.36 |
VAT with adjustment factor | 1.06383 | 6.00% = | Tk. | 70.49 |
|
| Grand Total = | Tk. | 1,174.85 |
|
| Rate per sqm = | Tk. | 117.49 |
Say, | Tk. 117 .00 per sqm |
|
| |
|
|
|
|
|
Item No. 32.48.1 |
|
|
|
|
Renewing standard acrylic emulsion paint (Plastic) to walls and ceiling: 2 coats |
|
|
|
|
Considering 10 sqm of work for 2 coats
| Tk. 202.00 | per liter = | Tk. | 202.00 |
| Tk. 600.00 | each = | Tk. | 450.00 |
| Tk. 390.00 | each = | Tk. | 292.50 |
|
| LS = | Tk. | 32.00 |
|
| LS = | Tk. | 96.00 |
|
| SubTotal = | Tk. | 1,072.50 |
| Contractor's profit | 10% = | Tk. | 107.25 |
| Overhead expenses | 3.50% = | Tk. | 37.54 |
|
| Total = | Tk. | 1,217.29 |
VAT with adjustment factor | 1.06383 | 6.00% = | Tk. | 77.70 |
|
| Grand Total = | Tk. | 1,294.99 |
|
| Rate per sqm = | Tk. | 129.50 |
Say, | Tk. 130 .00 per sqm |
|
| |