Contractor's profit Overhead expenses

10%

3.50%

=

=

Tk. Tk.

72.00

25.20

VAT with adjustment factor 1.06383

Total

6.00%

=

=

Tk. Tk.

817.20

52.16

 

Grand Total Rate per No.

=

=

Tk. Tk.

869.36

869.36

Say, Tk. 869 .00 each

 

 

 

 

 

 

 

 

Item No. 32.71.24

 

 

 

 

Supplying of the following items related to ARBORICULTURE work approved by the officer-in-charge

(x) Supply of Ripcord 400EC, 1 pics, 100ml bottle

 

 

 

 

Considering 100ml 1 bottle.

 

 

 

 

Cost of Ripcord 400EC 1.00 bottle @ Tk. 200.00

each

=

Tk.

200.00

Contractor's profit

10%

=

Tk.

20.00

Overhead expenses

3.50%

=

Tk.

7.00

 

Total

=

Tk.

227.00

VAT with adjustment factor 1.06383

6.00%

=

Tk.

14.49

 

Grand Total

=

Tk.

241.49

 

Rate per No.

=

Tk.

241.49

Say, Tk. 241 .00 each

 

 

 

 

 

 

 

 

Item No. 32.71.25

 

 

 

 

Supplying of the following items related to ARBORICULTURE work approved by the officer-in-charge

  1. Supply of Proclaim 5SG(emamectin benzoet) 1 box, (10 pack, each pack 10gm)

 

 

 

 

Considering 1 box (10gm 10 pack)

 

 

 

 

Proclaim 5SG 1.00 box @ Tk. 600.00

each

=

Tk.

600.00

Contractor's profit

10%

=

Tk.

60.00

Overhead expenses

3.50%

=

Tk.

21.00

 

Total

=

Tk.

681.00

VAT with adjustment factor 1.06383

6.00%

=

Tk.

43.47

 

Grand Total

=

Tk.

724.47

 

Rate per No.

=

Tk.

724.47

Say, Tk. 724 .00 each

 

 

 

 

 

 

 

 

Item No. 32.71.26

 

 

 

 

Supplying of the following items related to ARBORICULTURE work approved by the officer-in-charge

  1. Supply of Vertimec 018ECG (ebamectin) 1 pics, 50ml bottle

 

 

 

 

Considering 50ml 1 bottle.

 

 

 

 

Vertimec 018ECG 50ml 1.00 bottle @ Tk. 120.00

each

=

Tk.

120.00

Contractor's profit

10%

=

Tk.

12.00

Overhead expenses

3.50%

=

Tk.

4.20

 

Total

=

Tk.

136.20

VAT with adjustment factor 1.06383

6.00%

=

Tk.

8.69

 

Grand Total

=

Tk.

144.89

 

Rate per No.

=

Tk.

144.89

Say, Tk. 145 .00 each