Item No. 32.72.1

 

 

 

 

 

Painting earthen tub: 2 coats over a prime coat

(a) Earthen tub of 200mm and 250mm" size

 

 

 

 

 

Considering 1 No.

  1. Cost of paint

 

LS

=

Tk.

5.30

  1. Labour charge

 

LS

=

Tk.

6.50

  1. Tools and plant, sundries etc.

 

LS

=

Tk.

1.60

 

 

SubTotal

 

Tk.

13.40

 

Contractor's profit

10%

=

Tk.

1.34

 

Overhead expenses

3.50%

=

Tk.

0.47

 

 

Total

=

Tk.

15.21

VAT with adjustment factor

1.06383

6.00%

=

Tk.

0.97

 

 

Grand Total

=

Tk.

16.18

 

 

Rate per No.

=

Tk.

16.18

Say,

Tk. 16 .00 each

 

 

 

 

 

 

 

 

 

Item No. 32.72.2

 

 

 

 

 

Painting earthen tub: 2 coats over a prime coat

(b) Earthen tub of 300 mm, 350mm and 400 mm size

 

 

 

 

 

Considering 1 No.

  1. Cost of paint

 

LS

=

Tk.

10.60

  1. Labour charge

 

LS

=

Tk.

9.75

  1. Tools and plant, sundries etc.

 

LS

=

Tk.

1.60

 

 

SubTotal

 

Tk.

21.95

 

Contractor's profit

10%

=

Tk.

2.20

 

Overhead expenses

3.50%

=

Tk.

0.77

 

 

Total

=

Tk.

24.92

VAT with adjustment factor

1.06383

6.00%

=

Tk.

1.59

 

 

Grand Total

=

Tk.

26.51

 

 

Rate per No.

=

Tk.

26.51

Say,

Tk. 27 .00 each

 

 

 

 

 

 

 

 

 

Item No. 32.73.1

 

 

 

 

 

Levelling, dressing the plant/flower bed etc.

 

 

 

 

 

Considering 100 sqm of work

  1. Earth work: [PWD SoR 2018 Item No. 2.1.2

 

 

 

 

 

100 sqm x 0.15 m x 1/6 = 2.50 cum @

Tk. 73.03

per cum

=

Tk.

182.58

  1. Labour for levelling-dressin 1.00 no @

Tk. 320.00

each

=

Tk.

320.00

  1. Incidental, sundries

 

LS

=

Tk.

38.40

 

 

SubTotal

=

Tk.

540.98

 

Contractor's profit

10%

=

Tk.

54.10

 

Overhead expenses

3.50%

=

Tk.

18.93

 

 

Total

=

Tk.

614.01

VAT with adjustment factor

1.06383

6.00%

=

Tk.

39.19

 

 

Grand Total

=

Tk.

653.20

 

 

Rate per sqm

=

Tk.

6.53

Say,

Tk. 7 .00 sqm

 

 

 

 

 

 

 

 

 

Item No. 32.73.2

 

 

 

 

 

Lawn grass cutting, dressing, brooming and removing debris etc.

 

 

 

 

 

Considering 100 sqm of work

(a) Skilled labour for Grass cutting 1.50 no @

Tk. 390.00

per cum

=

Tk.

585.00