Item No. 32.72.1 |
|
|
|
|
|
Painting earthen tub: 2 coats over a prime coat (a) Earthen tub of 200mm and 250mm" size |
|
|
|
|
|
Considering 1 No.
|
| LS | = | Tk. | 5.30 |
|
| LS | = | Tk. | 6.50 |
|
| LS | = | Tk. | 1.60 |
|
| SubTotal |
| Tk. | 13.40 |
| Contractor's profit | 10% | = | Tk. | 1.34 |
| Overhead expenses | 3.50% | = | Tk. | 0.47 |
|
| Total | = | Tk. | 15.21 |
VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 0.97 |
|
| Grand Total | = | Tk. | 16.18 |
|
| Rate per No. | = | Tk. | 16.18 |
Say, | Tk. 16 .00 each |
|
|
| |
|
|
|
|
|
|
Item No. 32.72.2 |
|
|
|
|
|
Painting earthen tub: 2 coats over a prime coat (b) Earthen tub of 300 mm, 350mm and 400 mm size |
|
|
|
|
|
Considering 1 No.
|
| LS | = | Tk. | 10.60 |
|
| LS | = | Tk. | 9.75 |
|
| LS | = | Tk. | 1.60 |
|
| SubTotal |
| Tk. | 21.95 |
| Contractor's profit | 10% | = | Tk. | 2.20 |
| Overhead expenses | 3.50% | = | Tk. | 0.77 |
|
| Total | = | Tk. | 24.92 |
VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 1.59 |
|
| Grand Total | = | Tk. | 26.51 |
|
| Rate per No. | = | Tk. | 26.51 |
Say, | Tk. 27 .00 each |
|
|
| |
|
|
|
|
|
|
Item No. 32.73.1 |
|
|
|
|
|
Levelling, dressing the plant/flower bed etc. |
|
|
|
|
|
Considering 100 sqm of work
|
|
|
|
|
|
100 sqm x 0.15 m x 1/6 = 2.50 cum @ | Tk. 73.03 | per cum | = | Tk. | 182.58 |
| Tk. 320.00 | each | = | Tk. | 320.00 |
|
| LS | = | Tk. | 38.40 |
|
| SubTotal | = | Tk. | 540.98 |
| Contractor's profit | 10% | = | Tk. | 54.10 |
| Overhead expenses | 3.50% | = | Tk. | 18.93 |
|
| Total | = | Tk. | 614.01 |
VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 39.19 |
|
| Grand Total | = | Tk. | 653.20 |
|
| Rate per sqm | = | Tk. | 6.53 |
Say, | Tk. 7 .00 sqm |
|
|
| |
|
|
|
|
|
|
Item No. 32.73.2 |
|
|
|
|
|
Lawn grass cutting, dressing, brooming and removing debris etc. |
|
|
|
|
|
Considering 100 sqm of work (a) Skilled labour for Grass cutting 1.50 no @ | Tk. 390.00 | per cum | = | Tk. | 585.00 |