VAT with adjustment factor | Tk. 320.00 Contractor's profit Overhead expenses 1.06383 | each | = = | Tk. Tk. | 320.00 320.00 |
SubTotal 10% 3.50% | = = = | Tk. | 1,225.00 122.50 42.88 | ||
Total 6.00% | = = | Tk. Tk. | 1,390.38 88.75 | ||
Grand Total Rate per sqm | = = | Tk. Tk. | 1,479.13 14.79 | ||
Say, | Tk. 15 .00 sqm |
|
|
| |
|
|
|
|
|
|
Item No. 32.73.3 |
|
|
|
|
|
Spading, pulversing soil lump etc. |
|
|
|
|
|
Considering 100 sqm of work
| Tk. 320.00 | each | = | Tk. | 320.00 |
|
| LS | = | Tk. | 80.00 |
|
| SubTotal | = | Tk. | 400.00 |
| Contractor's profit | 10% | = | Tk. | 40.00 |
| Overhead expenses | 3.50% | = | Tk. | 14.00 |
|
| Total | = | Tk. | 454.00 |
VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 28.98 |
|
| Grand Total | = | Tk. | 482.98 |
|
| Rate per sqm | = | Tk. | 4.83 |
Say, | Tk. 5 .00 sqm |
|
|
| |
|
|
|
|
|
|
Item No. 32.74.1 |
|
|
|
|
|
Labour for picking-up and cleaning damaged bitumenous road surface |
|
|
|
|
|
Considering 100 sft of work (a) Labour 1.50 nos @ | Tk. 320.00 | each | = | Tk. | 480.00 |
|
| LS | = | Tk. | 38.40 |
|
| SubTotal | = | Tk. | 518.40 |
| Contractor's profit | 10% | = | Tk. | 51.84 |
| Overhead expenses | 3.50% | = | Tk. | 18.14 |
|
| Total | = | Tk. | 588.38 |
VAT with adjustment factor | 1.06383 | 6.00% | = | Tk. | 37.56 |
|
| Grand Total | = | Tk. | 625.94 |
|
| Rate per sqm | = | Tk. | 67.38 |
Say, | Tk. 67 .00 sqm |
|
|
| |
|
|
|
|
|
|
Item No. 32.74.2 |
|
|
|
|
|
Repairing the pot holes of the road by picking up and removing damaged materials with stone chips |
|
|
|
|
|
Considering 1 cum work
| Tk. 52.00 | per kg | = | Tk. | 5,200.00 |
| Tk. 158.90 | per cum | = | Tk. | 39.73 |
| Tk. 6,879.60 | per cum | = | Tk. | 6,191.64 |
| Tk. 200.00 | per mnd | = | Tk. | 540.00 |
0.5 - 1 ton capacity 0.50 day @ | Tk. 1,000.00 Tk. 3,000.00 | per day | = = | Tk. Tk. | 500.00 1,500.00 |
| Tk. 500.00 | per day | = | Tk. | 750.00 |
| Tk. 390.00 | per day | = | Tk. | 1,560.00 |
| Tk. 320.00 | per day | = | Tk. | 3,200.00 |
|
| LS | = | Tk. | 800.00 |
|
| SubTotal | = | Tk. | 20,281.37 |
| Contractor's profit | 10% | = | Tk. | 2,028.14 |