VAT with adjustment factor | Overhead expenses 3.50% | = | Tk. | 709.85 |
Total 1.06383 6.00% | = = | Tk. Tk. | 23,019.36 1,469.32 | |
Grand Total Rate per cum | = = | Tk. Tk. | 24,488.68 24,488.68 | |
Say, | Tk. 24,489 .00 cum |
| ||
|
|
|
|
|
Item No. 31.75 |
|
|
|
|
Applying necessary coat of bitumenous aluminium paint seal-coat on top surface of newly laid roofing felt |
|
|
|
|
Considering 100 sft of work
paint for 2 coats 0.30 gal @ | Tk. 1,364.00 per gal. | = | Tk. | 409.20 |
| LS | = | Tk. | 240.00 |
| LS | = | Tk. | 32.00 |
| SubTotal | = | Tk. | 681.20 |
| Contractor's profit 10% | = | Tk. | 68.12 |
| Overhead expenses 3.50% | = | Tk. | 23.84 |
| Total | = | Tk. | 773.16 |
VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 49.35 |
| Grand Total | = | Tk. | 822.51 |
| Rate per sqm | = | Tk. | 88.53 |
Say, | Tk. 89 .00 sqm |
|
|
|
|
|
|
|
|
Item No. 32.76.1 |
|
|
|
|
Supplying timber (unfinished) for repairing in wood works: Garjan/Jam/local Sal |
|
|
|
|
Considering 1 cft unfinished wood (Garjan/Jam/local Sal) |
|
|
|
|
Cost of unfinished wood 1.00 cft @ | Tk. 2,000.00 per cft | = | Tk. | 2,000.00 |
| Contractor's profit 10% | = | Tk. | 200.00 |
| Overhead expenses 3.50% | = | Tk. | 70.00 |
| Total | = | Tk. | 2,270.00 |
VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 144.89 |
| Grand Total | = | Tk. | 2,414.89 |
| Rate per cum | = | Tk. | 85,281.84 |
Say, | Tk. 85,282 .00 cum |
|
|
|
|
|
|
|
|
Item No. 32.76.2 |
|
|
|
|
Supplying timber (unfinished) for repairing in wood works: Jarul |
|
|
|
|
Considering 1 cft unfinished wood (Jarul) |
|
|
|
|
Cost of unfinished wood 1.00 cft @ | Tk. 1,800.00 per cft | = | Tk. | 1,800.00 |
| Contractor's profit 10% | = | Tk. | 180.00 |
| Overhead expenses 3.50% | = | Tk. | 63.00 |
| Total | = | Tk. | 2,043.00 |
VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 130.40 |
| Grand Total | = | Tk. | 2,173.40 |
| Rate per cum | = | Tk. | 76,753.62 |
Say, | Tk. 76,754 .00 cum |
|
|
|
|
|
|
|
|
Item No. 32.76.3 |
|
|
|
|
Supplying timber (unfinished) for repairing in wood works: Shilkorai/Chickrashi |
|
|
|
|
Considering 1 cft unfinished wood (Shilkorai/Chickrashi) |
|
|
|
|
Cost of unfinished wood 1.00 cft @ | Tk. 2,490.00 per cft | = | Tk. | 2,490.00 |
| Contractor's profit 10% | = | Tk. | 249.00 |
| Overhead expenses 3.50% | = | Tk. | 87.15 |
| Total | = | Tk. | 2,826.15 |