(c) T & P, consumables and sundries | LS | = | Tk. | 64.00 |
SubTotal Contractor's profit 10% Overhead expenses 3.50% | = = = | Tk. | 2,564.00 256.40 89.74 | |
Total | = | Tk. | 2,910.14 | |
VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 185.75 |
| Grand Total | = | Tk. | 3,095.89 |
| Rate per meter | = | Tk. | 103.20 |
Say, | Tk. 103 .00 per meter |
|
|
|
|
|
|
|
|
Item No. 32.90 |
|
|
|
|
Supplying, fitting-fixing 400 gallon capacity ferro-cement water tank |
|
|
|
|
Considering 1 No. tank (a) 400 gal. Capacity tank in/c installation 1.00 no @ | Tk. 6,500.00 each | = | Tk. | 6,500.00 |
(b) Carrying, incidental, sundries etc. | LS | = | Tk. | 320.00 |
| SubTotal | = | Tk. | 6,820.00 |
| Contractor's profit 10% | = | Tk. | 682.00 |
| Overhead expenses 3.50% | = | Tk. | 238.70 |
| Total | = | Tk. | 7,740.70 |
VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 494.09 |
| Grand Total | = | Tk. | 8,234.79 |
| Rate per No. | = | Tk. | 8,234.79 |
Say, | Tk. 8,235 .00 each |
|
|
|
|
|
|
|
|
Item No. 32.91 |
|
|
|
|
Taking out 40 mm dia tube-well pipe and strainer up to 70 m depth |
|
|
|
|
Considering 30 m pipe
| Tk. 500.00 each | = | Tk. | 1,000.00 |
| Tk. 320.00 each | = | Tk. | 1,280.00 |
| LS | = | Tk. | 256.00 |
| SubTotal | = | Tk. | 2,536.00 |
| Contractor's profit 10% | = | Tk. | 253.60 |
| Overhead expenses 3.50% | = | Tk. | 88.76 |
| Total | = | Tk. | 2,878.36 |
VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 183.73 |
| Grand Total | = | Tk. | 3,062.09 |
| Rate per meter | = | Tk. | 102.07 |
Say, | Tk. 102 .00 per meter |
|
|
|
|
|
|
|
|
Item No. 32.92 |
|
|
|
|
Labour for re-sinking 40 mm dia tube-well pipe |
|
|
|
|
Considering 30 m pipe
| Tk. 600.00 each | = | Tk. | 300.00 |
| Tk. 500.00 each | = | Tk. | 2,000.00 |
| Tk. 320.00 each | = | Tk. | 3,840.00 |
| LS | = | Tk. | 640.00 |
| SubTotal | = | Tk. | 6,780.00 |
| Contractor's profit 10% | = | Tk. | 678.00 |
| Overhead expenses 3.50% | = | Tk. | 237.30 |
| Total | = | Tk. | 7,695.30 |
VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 491.19 |
| Grand Total | = | Tk. | 8,186.49 |
| Rate per meter | = | Tk. | 272.88 |
Say, | Tk. 273 .00 per meter |
|
|
|