Prev Next
īģŋ

(c) T & P, consumables and sundries

LS

=

Tk.

64.00

SubTotal

Contractor's profit 10%

Overhead expenses 3.50%

=

=

=

Tk.
Tk.
Tk.

2,564.00

256.40

89.74

Total

=

Tk.

2,910.14

VAT with adjustment factor

1.06383 6.00%

=

Tk.

185.75

 

Grand Total

=

Tk.

3,095.89

 

Rate per meter

=

Tk.

103.20

Say,

Tk. 103 .00 per meter

 

 

 

 

 

 

 

 

Item No. 32.90

 

 

 

 

Supplying, fitting-fixing 400 gallon capacity ferro-cement water tank

 

 

 

 

Considering 1 No. tank

(a) 400 gal. Capacity tank

in/c installation 1.00 no @

Tk. 6,500.00 each

=

Tk.

6,500.00

(b) Carrying, incidental, sundries etc.

LS

=

Tk.

320.00

 

SubTotal

=

Tk.

6,820.00

 

Contractor's profit 10%

=

Tk.

682.00

 

Overhead expenses 3.50%

=

Tk.

238.70

 

Total

=

Tk.

7,740.70

VAT with adjustment factor

1.06383 6.00%

=

Tk.

494.09

 

Grand Total

=

Tk.

8,234.79

 

Rate per No.

=

Tk.

8,234.79

Say,

Tk. 8,235 .00 each

 

 

 

 

 

 

 

 

Item No. 32.91

 

 

 

 

Taking out 40 mm dia tube-well pipe and strainer up to 70 m depth

 

 

 

 

Considering 30 m pipe

  1. Tube-well mistry 2.00 nos @

Tk. 500.00 each

=

Tk.

1,000.00

  1. Ordinary labour 4.00 nos @

Tk. 320.00 each

=

Tk.

1,280.00

  1. T & P, consumables and sundries

LS

=

Tk.

256.00

 

SubTotal

=

Tk.

2,536.00

 

Contractor's profit 10%

=

Tk.

253.60

 

Overhead expenses 3.50%

=

Tk.

88.76

 

Total

=

Tk.

2,878.36

VAT with adjustment factor

1.06383 6.00%

=

Tk.

183.73

 

Grand Total

=

Tk.

3,062.09

 

Rate per meter

=

Tk.

102.07

Say,

Tk. 102 .00 per meter

 

 

 

 

 

 

 

 

Item No. 32.92

 

 

 

 

Labour for re-sinking 40 mm dia tube-well pipe

 

 

 

 

Considering 30 m pipe

  1. Tube-well Head mistry 0.50 no @

Tk. 600.00 each

=

Tk.

300.00

  1. Tube-well mistry 4.00 nos @

Tk. 500.00 each

=

Tk.

2,000.00

  1. Ordinary labour 12.00 nos @

Tk. 320.00 each

=

Tk.

3,840.00

  1. T & P and sundries

LS

=

Tk.

640.00

 

SubTotal

=

Tk.

6,780.00

 

Contractor's profit 10%

=

Tk.

678.00

 

Overhead expenses 3.50%

=

Tk.

237.30

 

Total

=

Tk.

7,695.30

VAT with adjustment factor

1.06383 6.00%

=

Tk.

491.19

 

Grand Total

=

Tk.

8,186.49

 

Rate per meter

=

Tk.

272.88

Say,

Tk. 273 .00 per meter