Prev Next
īģŋ

VAT with adjustment

factor 1.06383 6.00%

=

Tk.

573.78

Grand Total Rate per No.

=

=

Tk. Tk.

9,562.98

9,562.98

Say, Tk. 9,563 .00 each

 

 

 

 

 

 

Item No. 32.87.6

 

 

 

 

Clearing sludges & night soil from septic tank of up to 200 users

 

 

 

 

Considering 1 No. septic tank

  1. Sweeper FOR ODD JOB 12.00 use

@ Tk. 800.00 per use

=

Tk.

9,600.00

  1. Hire charge of cart 8.00 trip

@ Tk. 500.00 per trip

=

Tk.

4,000.00

(e) T & P, consumables and sundries

LS

=

Tk.

320.00

 

SubTotal

=

Tk.

13,920.00

 

Contractor's profit 10%

=

Tk.

1,392.00

 

Overhead expenses 3.50%

=

Tk.

487.20

 

Total

=

Tk.

15,799.20

VAT with adjustment

factor 1.06383 6.00%

=

Tk.

1,008.46

 

Grand Total

=

Tk.

16,807.66

 

Rate per No.

=

Tk.

16,807.66

 

Say, Tk. 16,808 .00 each

 

 

 

 

 

 

 

 

Item No. 32.87.7

 

 

 

Clearing sewege or similar hazardous substances & removing to a safe place/ distances

 

 

 

Considering 2 cum

  1. Sweeper FOR ODD JOB 2.00 use @ Tk. 800.00 per use

=

Tk.

1,600.00

  1. Hire charge of cart 1.00 trip

@ Tk. 500.00 per trip

=

Tk.

500.00

(e) T & P, consumables and sundries

LS

=

Tk.

320.00

 

SubTotal

=

Tk.

2,420.00

 

Contractor's profit 10%

=

Tk.

242.00

 

Overhead expenses 3.50%

=

Tk.

84.70

 

Total

=

Tk.

2,746.70

VAT with adjustment

factor 1.06383 6.00%

=

Tk.

175.32

 

Grand Total

=

Tk.

2,922.02

 

Rate per cum

=

Tk.

1,461.01

 

Say, Tk. 1,461 .00 per cum

 

 

 

 

 

 

 

 

Item No. 32.88

 

 

 

 

Clearing sludges & night soil from Inspection pit

 

 

 

 

Considering 1 No. pit

  1. Sweeper FOR ODD JOB 0.50 use

@ Tk. 800.00 per use

=

Tk.

400.00

  1. T & P, consumables and sundries

LS

=

Tk.

16.00

 

SubTotal

=

Tk.

416.00

 

Contractor's profit 10%

=

Tk.

41.60

 

Overhead expenses 3.50%

=

Tk.

14.56

 

Total

=

Tk.

472.16

VAT with adjustment

factor 1.06383 6.00%

=

Tk.

30.14

 

Grand Total

=

Tk.

502.30

 

Rate per No.

=

Tk.

502.30

 

Say, Tk. 502 .00 each

 

 

 

 

 

 

 

 

Item No. 32.89

 

 

 

 

Clearing sludges & night soil from RCC/PVC soil pipe & sewer line

 

 

 

 

Considering 30 m long RCC pipe

  1. Sweeper FOR ODD JOB 2.50 use

@ Tk. 800.00 per use

=

Tk.

2,000.00

  1. Hire charge of cart 1.00 trip

@ Tk. 500.00 per trip

=

Tk.

500.00