Prev Next


 

 

 

 

 

 

Cost per sqm

=

Tk.

362.21

C-19

STAIR CASE SLAB AND STEPS using STEEL shutter

 

 

 

 

 

 

 

 

 

Assuming 8'-9" long & 4'-0" wide stair

 

 

 

 

 

 

 

 

 

Shuttering Area:70.50 sft

 

 

 

 

 

 

 

 

 

8'- 9" x 4'-0" x 0'-6" =

17.50 cft

 

 

 

 

 

 

 

 

1/2 x 9 x 4'-0" x 0'-10" x 0'-6" =

7.56 cft

 

 

 

 

 

 

 

 

=

25.06 cft

 

 

 

 

 

 

 

(i)

1.5" x 1.5" x 1/4" M.S. angle for frame for slab and sides:

 

 

 

 

 

 

 

 

 

1 x 8 x 8'-9"=

70.00 rft

 

 

 

 

 

 

 

 

1 x 5 x 4'-4"=

21.65 rft

 

 

 

 

 

 

 

 

2 x 2 x 1'-0"=

4.00 rft

 

 

 

 

 

 

 

 

=

95.65 rft

 

 

 

 

 

 

 

 

Add 5% wastage=

4.78 rft

 

 

 

 

 

 

 

 

=

100.43 rft

 

 

 

 

 

 

 

 

@ 2.34 Ibs per rft=

235.01 Ibs

@

Tk.

24.94

per Ib

=

Tk.

5,861.15

(ii)

1" x 1" x 1/8" M.S. angle for steps:

 

 

 

 

 

 

 

 

 

9 x 2 x 4'-0"=

72.00 rft

 

 

 

 

 

 

 

 

9 x 2 x 6"=

9.00 rft

 

 

 

 

 

 

 

 

2 x 9 x 1'-0" =

18.00 rft

 

 

 

 

 

 

 

 

=

99.00 rft

 

 

 

 

 

 

 

 

Add 5% wastage=

4.95 rft

 

 

 

 

 

 

 

 

=

103.95 rft

 

 

 

 

 

 

 

 

@ 0.8 Ibs per rft =

83.16 Ibs

@

Tk.

24.94

per Ib

=

Tk.

2,074.01

(iii)

1.5" x 1/4" thick F.I. bar for stiffner and tie for frame for slab and side:

 

 

 

 

 

 

 

 

 

Stiffner: 5 x 8'-9"=

43.75 rft

 

 

 

 

 

 

 

 

7 x 4'-4"=

30.31 rft

 

 

 

 

 

 

 

 

2 x 7 x 1'-0" =

14.00 rft

 

 

 

 

 

 

 

 

Tie between two sides: 2 x 4'-4" =

8.67 rft

 

 

 

 

 

 

 

 

 

96.73 rft

 

 

 

 

 

 

 

 

Add 5% wastage=

4.84 rft

 

 

 

 

 

 

 

 

 

101.57 rft

 

 

 

 

 

 

 

 

@ 1.28 Ibs per rft'=

130.01 Ibs

@

Tk.

24.94

per Ib

=

Tk.

3,242.45

(iv)

1" x 1/8" F.I. bar for stiffner for frame for steps:

 

 

 

 

 

 

 

 

 

9 x 1 x 6"=

4.5 rft

 

 

 

 

 

 

 

 

Add 5% wastage=

0.23 rft

 

 

 

 

 

 

 

 

=

4.73 rft

 

 

 

 

 

 

 

 

(@ 0.425 Ibs per rft)=

2.01 Ibs

@

Tk.

24.94

per Ib

=

Tk.

50.13

(v)

16 BWG steel sheet for covering frame:

 

 

 

 

 

 

 

 

 

1 x 8'-9" x 4'-4"=

37.89 sft

 

 

 

 

 

 

 

 

2 x 8'-9" x 1'-0"=

17.50 sft

 

 

 

 

 

 

 

 

9 x 4'-0" x 6"=

18.00 sft

 

 

 

 

 

 

 

 

=

73.39 sft

 

 

 

 

 

 

 

 

Add 5% wastage=

3.6695 sft

 

 

 

 

 

 

 

 

=

77.06 sft

 

 

 

 

 

 

 

 

@ 2.44 Ibs per sft=

188.03 Ibs

@

Tk.

27.44

per Ib

=

Tk.

5,159.54

(vi)

Nut, bolts, J-hooks etc.

2.5 kg

@

Tk.

160.00

per kg

=

Tk.

400.00

(vii)

Fabrication of steel shutter:

73.39 sft

@

Tk.

75.00

per sft

=

Tk.

5,504.25

 

 

 

 

 

 

Total

=

Tk.

22,291.53

 

 

Considering 30 times use

 

 

 

=

Tk.

743.05

(viii)

2"/1.5" dia M.S props in/c adjustable mechanism with top and bottom plate

 

 

 

 

 

 

 

 

 

and locking arrangement etc.:

8 nos

@

Tk.

1,650.00

each

=

Tk.

13,200.00

(ix)

1.5" x 1.5" x 1/4" M.S. angle as cross bar:

 

 

 

 

 

 

 

 

 

4 x 5'-0"=

20.00 rft

 

 

 

 

 

 

 

 

Add 5% wastage=

1.00 rft

 

 

 

 

 

 

 

 

 

21.00 rft

 

 

 

 

 

 

 

 

@ 2.34 Ib per rft =

49.14 Ibs

@

Tk.

24.94

per Ib

=

Tk.

1,225.55