Add VAT with adjustment factor 1.06383 6.00% = | Tk. | 2,109.47 |
Grand Total = | Tk. | 35,157.76 |
Say, Tk. 35,158 .00 per tender | ||
|
|
|
Item No.- 01.2.5 |
|
|
Updating of Implementation Schedule prepared in M.S. Project software (CPM net working)
| Tk. | 12,000.00 |
| Tk. | 217.44 |
Sub - Total = | Tk. | 12,217.44 |
Profit 10.00% = | Tk. | 1,221.74 |
Overhead 3.50% = | Tk. | 427.61 |
Total = | Tk. | 13,866.79 |
Add VAT with adjustment factor 1.06383 6.00% = | Tk. | 885.11 |
Grand Total = | Tk. | 14,751.90 |
Say, Tk. 14,752 .00 each month |
|
|
|
|
|
Item No.- 01.2.6 |
|
|
Logistic support to monthly progress meeting between Contractor and Emplyer at the Engineer's office at site |
|
|
| Tk. | 1,800.00 |
| Tk. | 250.00 |
Sub - Total = | Tk. | 2,050.00 |
Profit 10.00% = | Tk. | 205.00 |
Overhead 3.50% = | Tk. | 71.75 |
Total = | Tk. | 2,326.75 |
Add VAT with adjustment factor 1.06383 6.00% = | Tk. | 148.52 |
Grand Total = | Tk. | 2,475.27 |
Say, Tk. 2,475 .00 each month |
|
|
|
|
|
Item No.- 01.3 |
|
|
Setting out: providing layout, bench-mark, property line, formation level etc. |
|
|
Considering 5000 sft ground area |
|
|
| Tk. | 1,400.00 |
| Tk. | 800.00 |
| Tk. | 950.00 |
| Tk. | 640.00 |
| Tk. | 4,600.00 |
| Tk. | 800.00 |
Sub - Total = | Tk. | 9,190.00 |
Profit 10.00% = | Tk. | 919.00 |
Overhead 3.50% = | Tk. | 321.65 |
Total = | Tk. | 10,430.65 |
Add VAT with adjustment factor 1.06383 6.00% = | Tk. | 665.79 |
Grand Total = | Tk. | 11,096.44 |
Rate per sft = | Tk. | 2.22 |
Rate per sqm = | Tk. | 23.90 |
Say, Tk. 24 .00 per sqm |
|
|
|
|
|
Item No.- 01.4 |
|
|
Mobilization, cleaning site before commencing actual physical works and demobilization on completion of work |
|
|
Considering a site of 5000 sft ground area |
|
|
| Tk. | 52,000.00 |
| Tk. | 13,000.00 |
Sub - Total = | Tk. | 65,000.00 |
Profit 10.00% = | Tk. | 6,500.00 |