Prev Next
īģŋ

Add VAT with adjustment factor 1.06383 6.00% =

Tk.

2,109.47

Grand Total =

Tk.

35,157.76

Say, Tk. 35,158 .00 per tender

 

 

 

Item No.- 01.2.5

 

 

Updating of Implementation Schedule prepared in M.S. Project software (CPM net working)

  1. Updating implementation schedule prepared 3 day @ Tk. 120,000.00 per month =
    in M.S. Project software

Tk.

12,000.00

  1. Printing : 3 set 12.08 sft @ Tk. 18.00 per sft =

Tk.

217.44

Sub - Total =

Tk.

12,217.44

Profit 10.00% =

Tk.

1,221.74

Overhead 3.50% =

Tk.

427.61

Total =

Tk.

13,866.79

Add VAT with adjustment factor 1.06383 6.00% =

Tk.

885.11

Grand Total =

Tk.

14,751.90

Say, Tk. 14,752 .00 each month

 

 

 

 

 

Item No.- 01.2.6

 

 

Logistic support to monthly progress meeting between Contractor and Emplyer at the Engineer's office at site

 

 

  1. Logistic support to arrange and conducting progress meeting LS =

Tk.

1,800.00

  1. Incidental, sundries etc. LS =

Tk.

250.00

Sub - Total =

Tk.

2,050.00

Profit 10.00% =

Tk.

205.00

Overhead 3.50% =

Tk.

71.75

Total =

Tk.

2,326.75

Add VAT with adjustment factor 1.06383 6.00% =

Tk.

148.52

Grand Total =

Tk.

2,475.27

Say, Tk. 2,475 .00 each month

 

 

 

 

 

Item No.- 01.3

 

 

Setting out: providing layout, bench-mark, property line, formation level etc.

 

 

Considering 5000 sft ground area

 

 

  1. Surveyor 1 no @ Tk. 1,400.00 per day =

Tk.

1,400.00

  1. Helper to surveyor 1 no @ Tk. 800.00 per day =

Tk.

800.00

  1. Hire charge of Level/Theodolite 1 set @ Tk. 950.00 per day =

Tk.

950.00

  1. Ordinary labour 2 nos @ Tk. 320.00 per day =

Tk.

640.00

  1. Cost for construct and protect bench-mark, test pit etc. LS =

Tk.

4,600.00

  1. Tools and plant, spike, nails, chalk-powder etc. LS =

Tk.

800.00

Sub - Total =

Tk.

9,190.00

Profit 10.00% =

Tk.

919.00

Overhead 3.50% =

Tk.

321.65

Total =

Tk.

10,430.65

Add VAT with adjustment factor 1.06383 6.00% =

Tk.

665.79

Grand Total =

Tk.

11,096.44

Rate per sft =

Tk.

2.22

Rate per sqm =

Tk.

23.90

Say, Tk. 24 .00 per sqm

 

 

 

 

 

Item No.- 01.4

 

 

Mobilization, cleaning site before commencing actual physical works and demobilization on completion of work

 

 

Considering a site of 5000 sft ground area

 

 

  1. Contractor's site office, store, stackyard, Labour shed, service connections, LS =
    toilet facilities etc. cleaning site

Tk.

52,000.00

  1. Cleaning and removal LS =

Tk.

13,000.00

Sub - Total =

Tk.

65,000.00

Profit 10.00% =

Tk.

6,500.00