Prev Next
īģŋ

Overhead 3.50% = Tk. 2,275.00

Total = Tk. 73,775.00

Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,709.04

Grand Total = Tk. 78,484.04

Rate per sft = Tk. 15.70

Rate per sqm = Tk. 168.99

Say, Tk. 169 .00 per sqm

Item No.- 01.5 Rate is directly taken from basic material rate

Item No.- 01.6 Rate is directly taken from basic material rate

Item No.- 01.7 Rate is directly taken from basic material rate

Item No.- 01.8

Supply, fitting, fixing operating & maintenance of the costruction supervision lift (1000Kg capacity) for supervision of building construction work. Number of month shall be calculated 1/2 (half) of the project period for new construction and full project period for vertical extension work.

Item No.- 01.8.1

6th to 10th floor

1. Cost of steel frame 5000 kg @ 111.49 per kg = Tk. 557,450.00

2. Cost of motor, car, gear box, push button, cable and necessary safety measures LS = Tk. 500,000.00

3. Deduction of resale value of the lift set 80% = Tk. 845,960.00

Cost of Complete set Sub-Total = Tk. 211,490.00

Installation charge of the complete lift system including the cost of RCC base and erection with necessary connections at every floor, fixing motors, car, cables gears etc. and commissioning

  1. RCC base construction of size 2.5 m x 2.5 m x 0.45 m= = Tk. 42,187.50
  2. Connection with anchor bolts at every floor, 4- bolts per floor) = Tk. 10,000.00
  3. Installation and commissioning LS = Tk. 50,000.00

4. Dismantling charge LS = Tk. 30,000.00

Sub - Total = Tk. 313,677.50

Cost per month considering 18 months project period hire charge will be applicable for half of the = Tk. 34,854.00

project period.

5. Maintenance and operation cost

  1. Trained operator LS = Tk. 10,000.00
  2. Maintenance & Electricity bill LS = Tk. 2,000.00

Sub - Total = Tk. 46,854.00

Profit 10.00% = Tk. 4,685.40

Overhead 3.50% = Tk. 1,639.89

Total = Tk. 53,179.29

Add VAT with adjustment factor 1.06383 6.00% = Tk. 3,394.42

Grand Total = Tk. 56,573.71

Cost per month considering 18 months project period hire charge will be applicable for half of the = Tk. 28,287.00

project period. (50% cost to be shared by contractor)

Say, Tk. 28,287 .00 per month

 

Item No.- 01.8.2

10th to 15th floor

1. Cost of steel frame 7500 kg @ 111.49 per kg = Tk. 836,175.00

2. Cost of motor, car, gear box, push button, cable and necessary safety measures LS = Tk. 550,000.00

3. Deduction of resale value of the lift set 75% = Tk. 1,039,631.25

Cost of Complete set Sub-Total = Tk. 346,543.75

Installation charge of the complete lift system including the cost of RCC base and erection with necessary connections at every floor, fixing motors, car, cables gears etc. and commissioning

  1. RCC base construction of size 2.5 m X 2.5 m X 0.45 m = = Tk. 42,187.50
  2. Connection with anchor bolts at every floor, 4- bolts per floor) = Tk. 15,000.00
  3. Installation and commissioning LS = Tk. 75,000.00

4. Dismantling charge LS = Tk. 45,000.00

Sub - Total = Tk. 523,731.25