Prev Next
īģŋ

Cost per month considering 21 months year project period hire charge will be applicable for half of the project period

4. Maintenance and operation cost

 

=

Tk.

49,880.00

  1. Trained operator

LS

=

Tk.

10,000.00

  1. Maintenance & Electricity bill

LS

=

Tk.

2,500.00

 

Sub - Total

=

Tk.

62,380.00

Profit

10.00%

=

 

6,238.00

Overhead

3.50%

=

 

2,183.30

 

Total

=

Tk.

70,801.30

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

4,519.23

 

Grand Total

=

Tk.

75,320.53

Cost per month considering 21 months year project period hire charge will be applicable for half of the project period. (50% cost to be shared by contractor)

 

=

Tk.

37,660.50

Say, Tk. 37,661

.00 per month

 

 

 

 

 

 

 

 

Item No.- 01.8.3

 

 

 

 

15th to 20th floor

1. Cost of steel frame 10000 kg @ 111.49

per kg

=

Tk.

1,114,900.00

2. Cost of motor, car, gear box, push button, cable and necessary safety measures

LS

=

Tk.

600,000.00

3. Deduction of resale value of the lift set

70%

=

Tk.

1,200,430.00

Cost of complete set

Sub-Total

=

Tk.

514,470.00

Installation charge of the complete lift system including the cost of RCC base and erection with necessary connections at every floor, fixing motors, car, cables gears etc. and commissioning

  1. RCC base construction of size 2.5 m X 2.5 m X 0.45 m=

 

=

Tk.

42,187.50

  1. Connection with anchor bolts at every floor, 4- bolts per floor)

 

=

Tk.

20,000.00

  1. Installation and commissioning

LS

=

Tk.

100,000.00

4. Dismantling charge

LS

=

Tk.

60,000.00

 

Sub - Total

=

Tk.

736,657.50

Cost per month Considering 24 months project period hire charge will be applicable for half of the project period

=

Tk.

61,389.00

5. Maintenance and operation cost

  1. Trained operator LS

=

Tk.

10,000.00

  1. Maintenance & Electricity bill

LS

=

Tk.

3,000.00

 

Sub - Total

=

Tk.

74,389.00

Profit

10.00%

=

Tk.

7,438.90

Overhead

3.50%

=

Tk.

2,603.62

 

Total

=

Tk.

84,431.52

Add VAT with adjustment factor 1.06383

6.00%

=

Tk.

5,389.25

 

Grand Total

=

Tk.

89,820.77

Cost per month considering 24 months project period hire charge will be applicable for half of the project period. (50% cost to be shared by contractor)

 

=

Tk.

44,910.50

Say, Tk. 44,911

.00 per month

 

 

 

 

 

 

 

 

Item No.- 01.8.4

 

 

 

 

20th to 25th floor

1. Cost of steel frame 12500 kg @ 111.49

 

=

Tk.

1,393,625.00

2. Cost of motor, car, gear box, push button, cable and necessary safety measures

LS

=

Tk.

675,000.00

3. Deduction of resale value of the lift set

65%

=

Tk.

1,344,606.25

Cost of Complete set

Sub-Total

=

Tk.

724,018.75

Installation charge of the complete lift system including the cost of RCC base and erection with necessary connections at every floor, fixing motors, car, cables gears etc. and commissioning

  1. RCC base construction of size 2.5 m X 2.5 m X 0.45 m =

 

=

Tk.

42,187.50

  1. Connection with anchor bolts at every floor, 4- bolts per floor)

 

=

Tk.

25,000.00

  1. Installation and commissioning

LS

=

Tk.

125,000.00

5. Dismantling charge

LS

=

Tk.

75,000.00

 

Sub - Total

=

Tk.

916,206.25

Cost per month Considering 27 months project period hire charge will be applicable for half of the project period (50% cost to be shared by contractor)

 

=

Tk.

67,868.00

4. Maintenance and operation cost