07.9.4 | Formwork/shuttering, prop and necessary supports etc. (steel) Padestals, column, column capitals, lift wall and walls upto Ground Floor (From Secondary Input : Item C-13) Add VAT with adjustment factor |
| Profit 1.06383 | per sqm 10.00% 3.50% | = = = | Tk. | 337.13 33.71 11.80 |
07.9.5 | |||||||
Total 6.00% | = = | Tk. Tk. | 382.64 24.42 | ||||
Grand Total | = | Tk. Tk. | 407.06 346.28 | ||||
Say, | Tk. |
| 408 .00 per sqm |
| |||
Formwork/shuttering, prop and necessary supports etc. (steel) |
|
| per sqm | = | |||
| Tie beam and lintels : Ground Floor |
| Profit | 10.00% | = | Tk. | 34.63 |
| (From Secondary Input : Item C-14) |
| Overhead | 3.50% | = | Tk. | 12.12 |
|
|
|
| Total | = | Tk. | 393.03 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 25.09 |
|
|
|
| Grand Total | = | Tk. | 418.12 |
07.9.6 | Say, | Tk. |
| 419 .00 per sqm |
| Tk. | 376.42 |
Formwork/shuttering, prop and necessary supports etc. (steel) |
|
| per sqm | = | |||
| Tee beams, Ell beams and Rectangular |
| Profit | 10.00% | = | Tk. | 37.64 |
| beams etc upto Ground Floor (Fro Seondary Inpt : Item C-15) |
| Overhead | 3.50% | = | Tk. | 13.17 |
|
|
|
| Total | = | Tk. | 427.23 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 27.27 |
|
|
|
| Grand Total | = | Tk. | 454.50 |
07.9.7 | Say, | Tk. |
| 455 .00 per sqm |
| Tk. | 440.57 |
Formwork/shuttering, prop and necessary supports etc. (steel) |
|
| per sqm | = | |||
| Floor and roof slab upto Ground Floor |
| Profit | 10.00% | = | Tk. | 44.06 |
| (From Secondary Input : Item C-16) |
| Overhead | 3.50% | = | Tk. | 15.42 |
|
|
|
| Total | = | Tk. | 500.05 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 31.92 |
|
|
|
| Grand Total | = | Tk. | 531.97 |
07.9.8 | Say, | Tk. |
| 532 .00 per sqm |
| Tk. | 320.34 |
Formwork/shuttering, prop and necessary supports etc. (steel) |
|
| per sqm | = | |||
| Cornice, railing, drop walls, louver, fins etc. : Ground Floor |
| Profit | 10.00% | = | Tk. | 32.03 |
| (From Secondary Input : Item C-17) |
| Overhead | 3.50% | = | Tk. | 11.21 |
|
|
|
| Total | = | Tk. | 363.58 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 23.21 |
|
|
|
| Grand Total | = | Tk. | 386.79 |
07.9.9 | Say, | Tk. |
| 387 .00 per sqm |
| Tk. | 362.21 |
Formwork/shuttering, prop and necessary supports etc. (steel) |
|
| per sqm | = | |||
| Sunshade, false ceiling : Ground Floor |
| Profit | 10.00% | = | Tk. | 36.22 |
| (From Secondary Input : Item C-18) |
| Overhead | 3.50% | = | Tk. | 12.68 |
|
|
|
| Total | = | Tk. | 411.11 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 26.24 |
|
|
|
| Grand Total | = | Tk. | 437.35 |
07.9.10 | Say, | Tk. |
| 438 .00 per sqm |
| Tk. | 361.13 |
Formwork/shuttering, prop and necessary supports etc. (steel) |
|
| per sqm | = | |||
| Stair case slab and steps upto Ground Floor |
| Profit | 10.00% | = | Tk. | 36.11 |
| (From Secondary Input : Item C-19) |
| Overhead | 3.50% | = | Tk. | 12.64 |
|
|
|
| Total | = | Tk. | 409.88 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 26.16 |
|
|
|
| Grand Total | = | Tk. | 436.04 |
| Say, | Tk. |
| 437 .00 per sqm |
|
|
|