Prev Next


07.9.4

Formwork/shuttering, prop and necessary supports etc. (steel) Padestals, column, column capitals, lift wall and walls upto Ground Floor (From Secondary Input : Item C-13)

Add VAT with adjustment factor

 

Profit
Overhead

1.06383

per sqm

10.00%

3.50%

=

=

=

Tk.
Tk.
Tk.

337.13

33.71

11.80

07.9.5

Total

6.00%

=

=

Tk. Tk.

382.64

24.42

Grand Total

=

Tk.

Tk.

407.06

346.28

Say,

Tk.

 

408 .00 per sqm

 

Formwork/shuttering, prop and necessary supports etc. (steel)

 

 

per sqm

=

 

Tie beam and lintels : Ground Floor

 

Profit

10.00%

=

Tk.

34.63

 

(From Secondary Input : Item C-14)

 

Overhead

3.50%

=

Tk.

12.12

 

 

 

 

Total

=

Tk.

393.03

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

25.09

 

 

 

 

Grand Total

=

Tk.

418.12

07.9.6

Say,

Tk.

 

419 .00 per sqm

 

Tk.

376.42

Formwork/shuttering, prop and necessary supports etc. (steel)

 

 

per sqm

=

 

Tee beams, Ell beams and Rectangular

 

Profit

10.00%

=

Tk.

37.64

 

beams etc upto Ground Floor

(Fro Seondary Inpt : Item C-15)

 

Overhead

3.50%

=

Tk.

13.17

 

 

 

 

Total

=

Tk.

427.23

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

27.27

 

 

 

 

Grand Total

=

Tk.

454.50

07.9.7

Say,

Tk.

 

455 .00 per sqm

 

Tk.

440.57

Formwork/shuttering, prop and necessary supports etc. (steel)

 

 

per sqm

=

 

Floor and roof slab upto Ground Floor

 

Profit

10.00%

=

Tk.

44.06

 

(From Secondary Input : Item C-16)

 

Overhead

3.50%

=

Tk.

15.42

 

 

 

 

Total

=

Tk.

500.05

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

31.92

 

 

 

 

Grand Total

=

Tk.

531.97

07.9.8

Say,

Tk.

 

532 .00 per sqm

 

Tk.

320.34

Formwork/shuttering, prop and necessary supports etc. (steel)

 

 

per sqm

=

 

Cornice, railing, drop walls, louver, fins etc. : Ground Floor

 

Profit

10.00%

=

Tk.

32.03

 

(From Secondary Input : Item C-17)

 

Overhead

3.50%

=

Tk.

11.21

 

 

 

 

Total

=

Tk.

363.58

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

23.21

 

 

 

 

Grand Total

=

Tk.

386.79

07.9.9

Say,

Tk.

 

387 .00 per sqm

 

Tk.

362.21

Formwork/shuttering, prop and necessary supports etc. (steel)

 

 

per sqm

=

 

Sunshade, false ceiling : Ground Floor

 

Profit

10.00%

=

Tk.

36.22

 

(From Secondary Input : Item C-18)

 

Overhead

3.50%

=

Tk.

12.68

 

 

 

 

Total

=

Tk.

411.11

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

26.24

 

 

 

 

Grand Total

=

Tk.

437.35

07.9.10

Say,

Tk.

 

438 .00 per sqm

 

Tk.

361.13

Formwork/shuttering, prop and necessary supports etc. (steel)

 

 

per sqm

=

 

Stair case slab and steps upto Ground Floor

 

Profit

10.00%

=

Tk.

36.11

 

(From Secondary Input : Item C-19)

 

Overhead

3.50%

=

Tk.

12.64

 

 

 

 

Total

=

Tk.

409.88

 

Add VAT with adjustment factor

 

1.06383

6.00%

=

Tk.

26.16

 

 

 

 

Grand Total

=

Tk.

436.04

 

Say,

Tk.

 

437 .00 per sqm