Grand Total = Tk. 6,901.47 Rate per kg = Tk. 138.03 |
Say, Tk. 138 .00 per kg |
|
Item No.- 08.4 |
Fabrication and supplying Fan hook of 5/8" dia M.S. rod in/c fitting fixing in RCC. Considering 1 No. fan-hook
= 2.01 Ibs @ Tk. 27.44 per Ib = Tk. 55.15
|
Sub - Total = Tk. 93.55 Profit 10.00% = Tk. 9.36 Overhead 3.50% = Tk. 3.27 |
Total = Tk. 106.18 Add VAT with adjustment factor 1.06383 6.00% = Tk. 6.78 |
Grand Total = Tk. 112.96 Rate per No. = Tk. 112.96 = |
Say, Tk. 113 .00 per no |
|
Item No.- 08.5.1 |
Supplying, fitting and fixing Ribbed (with non centre bulb) PVC water stopper of width approx. 250 mm and approx 9 mm thick, for immovable (non working) RCC joints, with 1.5" x 2.5" wooden batten at the top and bottom, binding with GI wire etc. Break-up for 20 rft Work
2 x 20'-0" x 1.5" x 2.5" = 1.00 cft Wastage 5% = 0.05 cft |
1.05 cft @ Tk. 500.00 per cft = Tk. 175.00 3. Carpentry work
4. Placing and removing wooden bit in/c cleaning RCC surface
5. Wastage of RCC work LS = Tk. 61.72 6. G.I. Wire, nails etc. LS = Tk. 16.25 7. Tools and plant, sundries etc. LS = Tk. 106.67 |
Sub - Total = Tk. 5,135.64 Profit 10.00% = Tk. 513.56 Overhead 3.50% = Tk. 179.75 |
Total = Tk. 5,828.95 Add VAT with adjustment factor 1.06383 6.00% = Tk. 372.06 |
Grand Total = Tk. 6,201.01 Rate per rft = Tk. 310.05 Rate per rm = Tk. 1,017.27 |
Say Tk. 1,017 .00 per meter |
|
Item No.- 08.5.2 |
Supplying, fitting and fixing Ribbed (with centre bulb) PVC water stopper of width approx. 250mm and approx 9mm thick, for immovable Break-up for 20 rft work
2 x 20'-0" x 1.5" x 2.5" = 1.00 cft Wastage 5% = 0.05 cft |
1.05 cft @ Tk. 500.00 per cft = Tk. 175.00 3. Carpentry work
4. Placing and removing wooden bit in/c cleaning RCC surface |