26.9.9 26.9.9.1 | Corner Basin 440x360x195 mm, 7.0kg by weight Light colour (Ivory, Alpine White, Grey, Pink, Blue, Aqua Verde) Considering 1 No. of fixture |
|
|
|
|
|
|
|
| ||
| |||||||||||
1. | Coloured wash-basin | 1 | no | @ | Tk. |
| 788.00 | each | = | Tk. | 788.00 |
2. | Accessories: |
|
|
|
|
|
|
|
|
|
|
32 mm dia PVC waste pipe | 1 | no | @ | Tk. |
| 150.00 | each | = | Tk. | 150.00 | |
Grating with brass coupling | 1 | no | @ | Tk. |
| 300.00 | each | = | Tk. | 300.00 | |
CP chain with rubber plug | 1 | no | @ | Tk. |
| 80.00 | each | = | Tk. | 80.00 | |
3. | Fitting fixing materials: |
|
|
|
|
|
|
|
|
|
|
(a) | Cement mortar (1:4) |
|
|
|
|
|
|
|
|
|
|
Cement | 0.01 | bag | @ | Tk. |
| 395.00 | per bag | = | Tk. | 3.95 | |
Sand (F.M. 1.2) | 0.05 | cft | @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 0.70 | |
(b) | CI brakets | 1 | pair | @ | Tk. |
| 115.00 | per pair | = | Tk. | 115.00 |
4. | Labour: |
|
|
|
|
|
|
|
|
|
|
Plumber | 0.15 | no | @ | Tk. |
| 600.00 | each | = | Tk. | 90.00 | |
Skilled labour | 0.2 | no | @ | Tk. |
| 390.00 | each | = | Tk. | 78.00 | |
Ordinary labour | 0.4 | no | @ | Tk. |
| 320.00 | each | = | Tk. | 128.00 | |
|
|
|
|
|
|
|
| Sub - Total | = | Tk. | 1,733.65 |
|
|
|
|
|
| Profit | 10.00% | = | Tk. | 173.37 | |
|
|
|
|
|
| Overhead | 3.50% | = | Tk. | 60.68 | |
|
|
|
|
|
|
|
| Total | = | Tk. | 1,967.70 |
|
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 125.60 | |||
|
|
|
|
|
|
|
| Grand Total | = | Tk. | 2,093.30 |
|
|
|
|
|
|
|
| Rate per No. | = | Tk. | 2,093.30 |
|
|
|
| Say, | Tk. |
| 2,093 .00 each |
|
|
| |
26.9.9.2 | Coloured ( Marble Shade) |
|
|
|
|
|
|
|
|
|
|
| Considering 1 No. of fixture |
|
|
|
|
|
|
|
|
|
|
1. | Coloured wash-basin | 1 | no | @ | Tk. |
| 1,024.40 | each | = | Tk. | 1,024.40 |
2. | Accessories: |
|
|
|
|
|
|
|
|
|
|
32 mm dia PVC waste pipe | 1 | no | @ | Tk. |
| 150.00 | each | = | Tk. | 150.00 | |
Grating with brass coupling | 1 | no | @ | Tk. |
| 300.00 | each | = | Tk. | 300.00 | |
CP chain with rubber plug | 1 | no | @ | Tk. |
| 80.00 | each | = | Tk. | 80.00 | |
3. | Fitting fixing materials: |
|
|
|
|
|
|
|
|
|
|
(a) | Cement mortar (1:4) |
|
|
|
|
|
|
|
|
|
|
Cement | 0.01 | bag | @ | Tk. |
| 395.00 | per bag | = | Tk. | 3.95 | |
Sand (F.M. 1.2) | 0.05 | cft | @ | Tk. |
| 1,400.00 | per % cft | = | Tk. | 0.70 | |
(b) | CI brakets | 1 | pair | @ | Tk. |
| 115.00 | per pair | = | Tk. | 115.00 |
4. | Labour: |
|
|
|
|
|
|
|
|
|
|
Plumber | 0.15 | no | @ | Tk. |
| 600.00 | each | = | Tk. | 90.00 | |
Skilled labour | 0.2 | no | @ | Tk. |
| 390.00 | each | = | Tk. | 78.00 | |
Ordinary labour | 0.4 | no | @ | Tk. |
| 320.00 | each | = | Tk. | 128.00 | |
|
|
|
|
|
|
|
| Sub - Total | = | Tk. | 1,970.05 |
|
|
|
|
|
| Profit | 10.00% | = | Tk. | 197.01 | |
|
|
|
|
|
| Overhead | 3.50% | = | Tk. | 68.95 | |
|
|
|
|
|
|
|
| Total | = | Tk. | 2,236.01 |
|
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 142.72 | |||
|
|
|
|
|
|
|
| Grand Total | = | Tk. | 2,378.73 |
|
|
|
|
|
|
|
| Rate per No. | = | Tk. | 2,378.73 |
|
|
|
| Say, | Tk. |
| 2,379 .00 each |
|
|
| |
26.9.9.3 | Special coloured ( Deep Blue, Ruby, Rain Forest, Green), Considering 1 No. of fixture |
|
|
|
|
|
|
|
|
| |
| |||||||||||
1. | Coloured wash-basin | 1 | no | @ | Tk. |
| 1,182.00 | each | = | Tk. | 1,182.00 |
2. | Accessories: |
|
|
|
|
|
|
|
|
|
|
32 mm dia PVC waste pipe | 1 | no | @ | Tk. |
| 150.00 | each | = | Tk. | 150.00 | |
Grating with brass coupling | 1 | no | @ | Tk. |
| 300.00 | each | = | Tk. | 300.00 | |
CP chain with rubber plug | 1 | no | @ | Tk. |
| 80.00 | each | = | Tk. | 80.00 | |
3. | Fitting fixing materials: |
|
|
|
|
|
|
|
|
|
|
(a) | Cement mortar (1:4) |
|
|
|
|
|
|
|
|
|
|
(i) | Cement | 0.01 | bag | @ | Tk. |
| 395.00 | per bag | = | Tk. | 3.95 |