Rate for each

=

Tk.

29.44

Say, Tk. 29 .00 each

 

 

 

 

 

 

Item No. 32.39.2

 

 

 

 

Replacing 75 mm dia brass ring

 

 

 

 

Considering 1 No. brass hinge

  1. 75 mm dia brass ring 1.00 no @ Tk. 40.00

each

=

Tk.

40.00

  1. Labour charge

LS

=

Tk.

9.38

 

SubTotal

=

Tk.

49.38

Contractor's profit

10%

=

Tk.

4.94

Overhead expenses

3.50%

=

Tk.

1.73

 

Total

=

Tk.

56.05

VAT with adjustment factor 1.06383

6.00%

=

Tk.

3.58

 

Grand Total

=

Tk.

59.63

 

Rate for each

=

Tk.

59.63

Say, Tk. 60 .00 each

 

 

 

 

 

 

 

 

Item No. 32.40.1

 

 

 

 

Supplying, fitting and fixing expanded mesh metal net of 25 x 25 mm mesh in wooden or steel frame excluding cos of wood or steel sections and painting.

 

 

 

 

Considering 1.83 x 1.83 m = 3.35 sqm of work excluding cost of frame

  1. 25 x 25 mesh of expanded mesh

metal net in/c wastage, lap etc. 3.80 sqm @ Tk. 100.00

per kg

=

Tk.

380.00

  1. Nails, screws etc.

LS

=

Tk.

33.33

  1. 4"x 1.5" x 1/8" size clamp 4.00 nos @ Tk. 10.50
  2. Labour charge in/c

fitting-fixing in position 3.35 sqm @ Tk. 600.00

each
LS

=

=

Tk. Tk.

42.00

2,010.00

  1. T & P, scaffolding & sundries

LS

=

Tk.

80.00

 

SubTotal

=

Tk.

2,545.33

Contractor's profit

10%

=

Tk.

254.53

Overhead expenses

3.50%

=

Tk.

89.09

 

Total

=

Tk.

2,888.95

VAT with adjustment factor 1.06383

6.00%

=

Tk.

184.40

 

Grand Total

=

Tk.

3,073.35

 

Rate per sqm

=

Tk.

917.42

Say, Tk. 917 .00 per sqm

 

 

 

 

 

 

 

 

Item No. 32.40.2

 

 

 

 

25 mm expanded mesh metal net in F.I. Bar frame

 

 

 

 

Considering 1.83 x 1.83 m = 3.35 sqm of work

  1. 1" expanded mesh metal net 3.80 sqm @ Tk. 100.00

per kg

=

Tk.

380.00

  1. 4"x 1.5" x 1/8" size clamp 4.00 nos @ Tk. 14.00

each

=

Tk.

56.00

  1. Welding, reveting etc.
  2. 1" x 0.25" F.I. Bar

12 x 6'-0"= 72.00 rft

@ 0.85 Ibs per rft= 61.20 Ibs

LS

=

Tk.

300.00

Add 5% wastage = 3.06 Ibs

per Ibs
LS

=

=

Tk. Tk.

1,602.64

2,261.25

64.26 Ibs @ Tk. 24.94

  1. Labour charge for making

& fitting-fixing 3.35 sqm @ Tk. 675.00

  1. T & P, local carriage, sundries

LS

=

Tk.

80.00

 

SubTotal

=

Tk.

4,679.89

Contractor's profit

10%

=

Tk.

467.99

Overhead expenses

3.50%

=

Tk.

163.80

 

Total

=

Tk.

5,311.68