Item No. 32.106

 

 

 

Per day rate for Aluminium fabricator Considering 1 No. fabricator

 

 

 

a) Aluminium fabricator 1 no @

Tk. 1,000.00 Per day =

Tk.

1,000.00

 

Contractor's profit 10% =

Tk.

100.00

 

Overhead expenses 3.50% =

Tk.

35.00

 

Total =

Tk.

1,135.00

VAT with adjustment factor

1.06383 6.00% =

Tk.

72.45

 

Grand Total =

Tk.

1,207.45

 

Rate per day =

Tk.

1,207.45

Say,

Tk. 1,207 .00 per day

 

 

 

 

 

 

Item No. 32.107

 

 

 

Supply of essential hard wares and consumables for repairing aluminium door window frame and shutter, partition etc

 

 

Item No. 32.107.1

 

 

 

Supply of Swing door clouser

 

 

 

Cost of Swing door clouser 1 no @

Tk. 2,700.00 per set =

Tk.

2,700.00

 

Contractor's profit 10% =

Tk.

270.00

 

Overhead expenses 3.50% =

Tk.

94.50

 

Total =

Tk.

3,064.50

VAT with adjustment factor

1.06383 6.00% =

Tk.

195.61

 

Grand Total =

Tk.

3,260.11

 

Rate per set =

Tk.

3,260.11

Say,

Tk. 3,260 .00 each

 

 

 

 

 

 

Item No. 32.107.2

 

 

 

Supply of Swing door lock

 

 

 

Cost of Swing door lock 1 no @

Tk. 625.00 per set =

Tk.

625.00

 

Contractor's profit 10% =

Tk.

62.50

 

Overhead expenses 3.50% =

Tk.

21.88

 

Total =

Tk.

709.38

VAT with adjustment factor

1.06383 6.00% =

Tk.

45.28

 

Grand Total =

Tk.

754.66

 

Rate per set =

Tk.

754.66

Say,

Tk. 755 .00 each

 

 

 

 

 

 

Item No. 32.107.3

 

 

 

Supply of Swing door Mohiar

 

 

 

Cost of Swing door Mohiar 1 meter @

Tk. 16.41 per meter =

Tk.

16.41

 

Contractor's profit 10% =

Tk.

1.64

 

Overhead expenses 3.50% =

Tk.

0.57

 

Total =

Tk.

18.62

VAT with adjustment factor

1.06383 6.00% =

Tk.

1.19

 

Grand Total =

Tk.

19.81

 

Rate per meter =

Tk.

19.81

Say,

Tk. 20 .00 per meter

 

 

 

 

 

 

Item No. 32.107.4

 

 

 

Supply of Fixed Neoprene

 

 

 

Cost of Fixed Neoprene 1 meter @

Tk. 8.53 per meter =

Tk.

8.53

 

Contractor's profit 10% =

Tk.

0.85