(f) B-4 | Local carriage, sundries, T & P, water, laboratory charge etc. Concrete (1:2:4) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2 Considering 100 cft of work |
| LS = | Tk. | 320.00 |
| Total = 166.28 | Tk. | 16,628.00 | ||
19 mm down size |
|
|
|
| |
| crushed stone chips 87 cft | @ Tk. 19,500.00 | per % cft = | Tk. | 16,965.00 |
Sand (F.M. 2.2) 43.5 cft | @ Tk. 4,500.00 | per % cft = | Tk. | 1,957.50 | |
Cement: OPC, Type-1 (CEM-I),52.5 18 bags | @ Tk. 415.00 | per bag = | Tk. | 7,470.00 | |
Local carriage, sundries, T & P, water, laboratory charge etc. |
| LS = | Tk. | 320.00 | |
|
| Total of A. | = | Tk. | 26,712.50 |
|
|
| 267.13 |
|
|
B-5 | Concrete (1:1.5:3) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2 |
|
|
|
|
| Considering 100 cft of work |
|
|
|
|
19 mm down crushed stone chips 83 cft | @ Tk. 19,500.00 | per % cft = | Tk. | 16,185.00 | |
Sand (F.M. 2.2) 41.5 cft | @ Tk. 4,500.00 | per % cft = | Tk. | 1,867.50 | |
Cement: OPC, Type-1 (CEM-I), 52.5 22 bags | @ Tk. 415.00 | per bag = | Tk. | 9,130.00 | |
Local carriage, sundries, T & P, water, laboratory charge etc. | LS | = | Tk. | 320.00 | |
|
| Total (A) | = | Tk. | 27,502.50 |
|
|
| 275.03 |
|
|
B-6 | Concrete (1:1.25:2.5) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2 |
|
|
|
|
| Break-up for 100 cft |
|
|
|
|
19 mm down well graded |
|
|
|
| |
| crushed stone chips 80 cft | @ Tk. 19,500.00 | per % cft = | Tk. | 15,600.00 |
Well graded Sylhet sand (F.M. 2.2) 40 cft | @ Tk. 4,500.00 | per % cft = | Tk. | 1,800.00 | |
Cement: OPC, Type-1 (CEM-I),52.5 25.25 bags | @ Tk. 415.00 | Per bag = | Tk. | 10,478.75 | |
Local carriage, sundries, T & P, water, laboratory charge etc. |
| LS = | Tk. | 320.00 | |
|
|
| = | Tk. | 28,198.75 |
|
|
| 281.9875 pcft |
|
|
B-7 | Concrete (1:1:2) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2 |
|
|
|
|
| Break-up for 100 cft |
|
|
|
|
19 mm down well graded |
|
|
|
| |
| crushed stone chips 76 cft | @ Tk. 19,500.00 | per % cft = | Tk. | 14,820.00 |
Well graded Sylhet sand (F.M. 2.2) 38 cft | @ Tk. 4,500.00 | per % cft = | Tk. | 1,710.00 | |
Cement: OPC, Type-1 (CEM-I),52.5 30 bags | @ Tk. 415.00 | Per bag = | Tk. | 12,450.00 | |
Local carriage, sundries, T & P, water, laboratory charge etc. |
| LS = | Tk. | 320.00 | |
|
|
| = | Tk. | 29,300.00 |
|
|
| 293 pcft |
|
|
B-8 | Fair-Face Concrete (1:1.5:3) work with CRUSHED STONE CHIPS, 75% grey cement, 25% white cement and 100% sand of F.M. 2.2 Considering 100 cft of work |
|
| ||
19 mm down crushed stone chips 83 cft | @ Tk. 19,500.00 | per % cft = | Tk. | 16,185.00 | |
Sand (F.M. 2.2) 41.5 cft | @ Tk. 4,500.00 | per % cft = | Tk. | 1,867.50 | |
Cement: OPC, Type-1 (CEM-I), 52.5 16.5 bags | @ Tk. 415.00 | per bag = | Tk. | 6,847.50 | |
White Cement 275 kg | @ Tk. 26.00 | per kg = | Tk. | 7,150.00 | |
Colouring Pigment | LS |
| Tk. | 840.00 | |
Local carriage, sundries, T & P, water, laboratory charge etc. | LS | = | Tk. | 320.00 | |
|
| Total (A) | = | Tk. | 33,210.00 |
|
|
| 332.10 pcft |
|
|
| FORMWORK AND SUPPORTS |
|
|
|
|
C-1 | FOOTINGS OF COLUMN at plinth level using WOODEN shutter |
|
|
|
|
| Considering 6'-0'' x 6'-0'' Base (D =1 4'', d = 10'') 24 | 6 6 |
|
|
|
| Shuttering Area: 4 x 6'-0" x 1'-0" = 24 sft |
|
|
|
|
(i) | Plank and batten |
|
|
|
|
| 4 x 6'-0" x 1'-0" x 1" = 2.00 cft |
|
|
|
|
| 15% for batten, supports & wastage = 0.30 cft | @ Tk. 500.00 | per cft |
|
|
= 2.30 cft | |||||